| Date | Event | Completed |
|---|
| February 13, 2009 | H.R. 1 passed by the House of Representatives. |  |
| February 13, 2009 | H.R. 1 passed by the Senate. |  |
| February 17, 2009 | H.R. 1 Signed into law, and site goes live. |  |
| February 19, 2009 | Federal agencies to begin reporting their formula block grant awards. |  |
| March 03, 2009 | Federal agencies to begin reporting on their use of funds. |  |
| May 01, 2009 | Draft Agency and Program Plans Completed. |  |
| May 15, 2009 | Final Agency and Program Plans submitted to Office of Management and Budget. |  |
| May 17, 2009 | Agency and Program Plans posted on Recovery.gov. |  |
| May 18, 2009 | President to report to Congress on the progress of projects in compliance with the National Environmental Policy Act. |  |
| August 17, 2009 | Early Registration begins for Recipient Reporting. |  |
| September 10, 2009 | Council of Economic Advisers begin Quarterly Reporting. |  |
| October 01, 2009 | Recipient Reporting Begins. |  |
| October 10, 2009 | Recipient Reporting Ends. |  |
| October 15, 2009 | Recipient Federal Contract Data Posted. |  |
| October 30, 2009 | Recipient Grant and Loan Data Posted. |  |
| January 01, 2010 | Recipient Reporting Begins |  |
| January 10, 2010 | Recipient Reporting Ends |  |
| January 16, 2010 | Recipients Review and Correct Reports |  |
| January 23, 2010 | Federal Agencies Review and Comment on Reports |  |
| January 29, 2010 | Reporting Period Ends |  |
| January 30, 2010 | Recipient Data Posted on Recovery.gov |  |
| February 02, 2010 | Recipients Continue to Correct Reports until 3/17/10 |  |
| March 17, 2010 | Final Second Reporting Period Data Posted |  |
| April 01, 2010 | Third Recipient Reporting Cycle Begins |  |
| April 10, 2010 | Third Recipient Reporting Cycle Ends |  |
| April 11, 2010 | Recipients Review Reports |  |
| April 13, 2010 | Federal Agencies Review Reports |  |
| April 29, 2010 | Recipient/Federal Agency Review Ends |  |
| April 30, 2010 | Third Recipient Reporting Cycle Data Posted on Recovery.gov |  |
| May 03, 2010 | Continous Quality Assurance Period Begins |  |
| June 14, 2010 | Continuous Quality Assurance Period Ends |  |
| June 15, 2010 | Final 1st Quarter 2010 Recipient Reported Data Posted on Recovery.gov |  |
| July 01, 2010 | Recipient Reporting Begins |  |
| July 10, 2010 | Recipient Reporting Ends |  |
| August 03, 2010 | Continuous Quality Assurance Begins |  |
| September 21, 2010 | Continuous Quality Assurance for Q2 2010 Complete |  |
| September 22, 2010 | Recovery.gov Updated with Period 4 changes |  |
| October 01, 2010 | Recipient Reporting Begins |  |
| October 10, 2010 | Recipient Reporting Ends |  |
| November 02, 2010 | Continuous Quality Assurance Begins |  |
| December 06, 2010 | Continuous Quality Assurance for Q3 2010 Complete |  |
| December 08, 2010 | Final 3rd Quarter 2010 Recipient Reported Data Posted on Recovery.gov |  |
| January 01, 2011 | Recipient Reporting for Q4 2010 Begins |  |
| January 11, 2011 | Extended Reporting Cycle Begins |  |
| January 31, 2011 | Continuous Quality Assurance for Q4 2010 Begins |  |
| March 21, 2011 | Continuous Quality Assurance for Q4 2010 Complete | |
| March 23, 2011 | Final 4th Quarter 2010 Recipient Reported Data Posted on Recovery.gov | |
| April 01, 2011 | Recipient Reporting for Q1 2011 Begins | |