Grants - AWARD SUMMARY


MASSACHUSETTS TECHNOLOGY PARK


MBI's MassBroadband 123 project builds an open access high speed fiber optic internet infrastructure serving 123 western and north central Massachusetts communities connecting local businesses to new customers, students to learning opportunities, and first responders to vital information. This network provides the essential foundation for economic growth and stability to this distressed region.

Clarification of Codes

Choose a quarter and click "Go."


AWARD OVERVIEW

AWARD OVERVIEW
Award Number NT10BIX5570070 Funding Agency Department of Commerce
Total Award Amount $45,445,444 Project Location - City Westborough
Award Date 06/28/2010 Project Location - State MA
Project Status More than 50% Completed Project Location - Zip 01581-9999
Jobs Reported 103.91 Congressional District 02
Project Location - Country US

Recipient Information (Grants)

Recipient Information (Grants)
Recipient Name MASSACHUSETTS TECHNOLOGY PARK
Recipient DUNS Number 147368641
Recipient Address 75 NORTH DR
Recipient City WESTBOROUGH
Recipient State Massachusetts
Recipient Zip 01581-3335
Recipient Congressional District 02
Recipient Country USA
Required to Report Top 5
Highly Compensated Officials
No

Projects and Jobs Information

Projects and Jobs Information
Project Title Massachusetts Broadband 123
Project Status More than 50% Completed
Final Project Report Submitted No
Project Activities Description Power and Communication Line and Related Structures Construction
Quarterly Activities/Project Description 1.Executed overlash agreement with Russell Muni. Cable TV & Internet. 2.Executed pole attachment agreement with Time Warner Cable Northeast, LLC. 3.Executed Indefeasible Rights of Use agreement with Chicopee Elec. Light Dept. 4.Executed Indefeasible Rights of Use agreement with Holyoke Gas & Elec. Dept. 5.Executed permitting agreement with Pan Am Railways. 6.Executed permitting agreement with New England Central Railroad. 7.Received 3,002 Verizon pole licenses for a total of 31,603 (96%). 8.Received 3,218 electric utility pole licenses for a total of 29,428 (97%). 9.Released 155 fully-licensed fiber miles to construction for aerial installation for a total of 895 miles for the project (96%). 10.Installed 305 miles of messenger strand for a total of 775 miles for the project (83%). 11.Installed 388 miles of aerial fiber optic cable for a total of 676 miles for the project (72%). 12.Received licenses for 14 miles conduit for a total of 39 miles to date (93% complete). 13.Installed 8,131 feet of conduit for a total of 15,312 feet for the project (32%). 14.Completed designs for 8 Community Anchor Institutions for a total of 790 locations (97%). 15.Completed 44 Community Anchor Institution site installations for a total of 582 locations for the project (72%). 16.Completed 81 Community Anchor Institution fiber terminations for a total of 260 locations for the project (32% of locations complete). 17.Completed 6 Point of Interconnection and collocation site installations for a total of 17 to date (63%). 18.Completed turnover of first network segment to Network Operator, connecting 3 Points of Interconnection and 2 regeneration sites. 19.Executed 4 Letters of Intent with an Internet Service Providers for a total of 31, as well as signing 5 connecting agreements to total 13 connecting agreements for the project. 20.Submitted 4th formal Award Action Request for modifications of construction plans pending NTIA approval of route adjustments.
Jobs Created 103.91
Description of Jobs Created The Total Number of Jobs Created or Retained includes the following positions: 1. The Massachusetts Broadband Institute under the Massachusetts Technology Collaborative jobs counted are comprised of various administrative and program positions. They are: Director, Deputy Director, Program Director, Outreach Manager, Procurement Leads, Executive Assistant, Geographic Information Systems Analysts, Geographic Information Systems Manager, Interns and Federal Compliance Manager. 2. The Massachusetts Technology Collaborative Vendor Jobs Created or Retained for Professional Services Consultants providing programmatic, construction management, project management, technical, design adn engineering, make ready, construction, and auditing services to the Massachusetts Broadband Institute. 3. This grant does not have Sub Recipients at this time. Each position created and retained by the Massachusetts Technology Collaborative and its vendors is essential in carrying out the goals and objectives outlined in the grant award to build an open access high speed fiber optic network infrastructure. This infrastructure serves over 120 western and north central Massachusetts communities and provides the essential foundation for economic growth and stability to this distressed region.


Purchaser Information (Grants)

Purchaser Information
Contracting Office ID Not Reported
Contracting Office Name Not Available
Contracting Office Region Not Available
TAS Major Program 13-0554

Award Information

Award Information
Award Date 06/28/2010
Award Number NT10BIX5570070
Order Number
Award Type Grants
Funding Agency ID 13
Funding Agency Name Department of Commerce
Funding Office Name Not Available
Awarding Agency ID 13
Awarding Agency Name Department of Commerce
Amount of Award $45,445,444
Funds Invoiced/Received $33,101,603
Expenditure Amount $41,679,106
Infrastructure Expenditure Amount $41,679,106
Infrastructure Purpose and Rationale The purpose of the project is to construct the MassBroadband 123 network, a robust, open access, middle mile fiber network covering over one-third of the state will connect 123 communities in western and north central Massachusetts and the 1,392 community anchor institutions (CAIs) that serve them. MassBroadband 123 is the transformative missing link to deliver comprehensive economic, educational, and public safety benefits to this region hard hit by the national shift from manufacturing to a knowledge-based economy. The MassBroadband 123 solution comprehensively addresses the issues faced by the public safety community by creating a guaranteed-bandwidth public safety network that will interconnect the majority of municipal police, fire, and emergency management sites. This upgrade will make interoperability possible, significantly improving public safety responsiveness, coordination, and effectiveness. Additionally, the MassBroadband 123 network will dramatically change the economic development dynamic by bringing fiber within 3 miles of 99% of area businesses and directly connecting all the community colleges and most workforce development agencies. The project will bring broadband access to 11 NTIA defined economically distressed areas, and 69 communities designated by the state as Economic Target Areas, and will connect to 128 public housing sites to provide vulnerable residents with an important tool to find and compete for jobs. The MassBroadband 123 network primarily contributes to the following ARRA purposes: 1. To preserve and create jobs and promote economic recovery. 2. To assist those most impacted by the recession. 3. To invest in transportation, environmental protection, and other infrastructure that will provide long-term economic benefits.
Infrastructure Point of Contact Name Judy Dumont
Infrastructure Point of Contact Email dumont@masstech.org
Infrastructure Point of Contact Phone (508) 870-0312 x220
Infrastructure Point of Contact Address 75 North Drive
Infrastructure Point of Contact City Westborough
Infrastructure Point of Contact State MA
Infrastructure Point of Contact Zip 01581-3340

Product or Service Information (Grants)

Product or Service Information
Primary Activity Code 237130
Activity Description Power and Communication Line and Related Structures Construction

Sub-Awards Information

Sub-Awards Information
Sub-awards to Organizations 0
Sub-award Amounts to Organizations $0
Sub-Awards to Individuals 0
Sub-Award Amounts to Individuals $0
Number of Sub-awards less than $25,000/award 0
Amount of Sub-awards less than $25,000/award $0
Number of payments to vendors greater than $25,000 26
Total Amount of payments to vendors greater than $25,000/award $32,418,207
Number of payments to vendors less than $25,000/award 273
Total Amount of payments to vendors less than $25,000/award $800,265




Vendor Transactions

Time Warner - Award Number NT10BIX5570070 - Time Warner

Award Number NT10BIX5570070
Sub-Award Number N/A
Vendor DUNS Number Not reported
Vendor HQ Zip Code + 4 04401-0000
Vendor Name Time Warner
Product and Service Description Third party to the make-ready work needed on utility poles as stipulated in pole attachment agreements with Verizon,WMECO and Grid.
Payment Amount $167,418

UC Synergetic - Award Number NT10BIX5570070 - UC Synergetic

Award Number NT10BIX5570070
Sub-Award Number N/A
Vendor DUNS Number Not reported
Vendor HQ Zip Code + 4 29708-9708
Vendor Name UC Synergetic
Product and Service Description Provided services to perform surveys of route, including research on viability of underground route segments, and Community Anchor Institution (CAI) to be used in connection with development, procurement and construction of the MassBroadband 123 network.
Payment Amount $117,381

URS Corporation - Award Number NT10BIX5570070 - URS Corporation

Award Number NT10BIX5570070
Sub-Award Number N/A
Vendor DUNS Number Not reported
Vendor HQ Zip Code + 4 30281-0000
Vendor Name URS Corporation
Product and Service Description Preliminary engineering design firm required by Massachusetts General Laws Chapter 149A statue for design build procurements; Provided assistance with development of Design Build Request for Proposals. Supported procurement through its completion
Payment Amount $149,031

Verizon New England - Award Number NT10BIX5570070 - Verizon New England

Award Number NT10BIX5570070
Sub-Award Number N/A
Vendor DUNS Number Not reported
Vendor HQ Zip Code + 4 02110-0000
Vendor Name Verizon New England
Product and Service Description Primary telecommunication utility in project area. Costs incurred include applications and Make-Ready work needed on utility poles and conduits
Payment Amount $5,231,138

Western mass Electric - Award Number NT10BIX5570070 - Western mass Electric

Award Number NT10BIX5570070
Sub-Award Number N/A
Vendor DUNS Number Not reported
Vendor HQ Zip Code + 4 02110-0000
Vendor Name Western mass Electric
Product and Service Description Telecom utility in Mass Broadband 123 project area. Costs are for pole applications and Make Ready work
Payment Amount $2,224,049

Westfield Gas & Electric - Award Number NT10BIX5570070 - Westfield Gas & Electric

Award Number NT10BIX5570070
Sub-Award Number N/A
Vendor DUNS Number Not reported
Vendor HQ Zip Code + 4 01085-0990
Vendor Name Westfield Gas & Electric
Product and Service Description IRU Agreement
Payment Amount $72,800
<<<12>>>


Project Location Detail

Location Information
Latitude, Longitude 42º 17' 18", -71º 37' 44"
Congressional District 02
Address 1 75 North Drive
Address 2
City Westborough
County Worcester
State MA
Zip 01581-9999