Transport, set on the pre-prepared foundation, and tremie in place two (2) precast dam elements(precast elements will be previously constructed) designated as SS-1 ( 3700 Tons )and SBS-1 (4000 Tons) during the first "river season" which begins 1 June 2010. Total Tremie Concrete quantity for these two precast elements (AKA "shells") is estimated to be 4912 Cubic yards (CY). The total manhours (MH) expected to be expended to accomplish this task is 40,004. Prepatory work includes: drive 318 each (ea) 24" OD pipe piles (previously procured); furinsh, fabricate and install 1806 tons (TN) of reinforcing steel for tremie reinforcement; and furnish and install 362,786 Linear Feet (LF) of foundation underdrain system. Outfit and attach lifting frames for SS1 and SBS1. An additional 35,963 manhours will be required for offshore erection such as installing drill collar assemblies, master pile brackers, embedded metals and lines. The stimulus funding on this award was increased by $1,644,000 on March 17, 2010 which included the loading, setting, and tremie of two precast shells designated as SS-2 and SBS-2. The Stimulus funding was again increased by $6,025,000 on June 22, 2010. The Stimulus funding was increased in the 3rd Quarter of 2010 by $15,375,000 which included the loading and setting of precast shells designated as LP1 and LP2. The increased funds will be used to outfit and transport the precast shells into the river during the 2010-2011 river season. This will also cover the purchase, fabricate,and assembly of the precast shell lifting frames (#'s SBS-2 and SS1. There are an additional 75,417 craft manhours anticipated to complete this work, as well as 50,884 additional staff and supervision manhours.

Clarification of Codes

Choose a quarter and click "Go."


AWARD OVERVIEW

AWARD OVERVIEW
Award Number W912QR-04-C-0004 Funding Agency Corps of Engineers
Total Award Amount $27,941,413 Project Location - City Olmsted
Award Date 09/03/2009 Project Location - State IL
Project Status Completed Project Location - Zip 62970-2316
Jobs Reported 6.43 Congressional District 12
Project Location - Country US

Recipient Information (Contracts)

Recipient Information (Contracts)
Recipient Name WASHINGTON GROUP/ALBERICI JOINT VENTURE
Recipient DUNS Number 141315353
Recipient Address 675 NEW DAM RD
Recipient City OLMSTED
Recipient State Illinois
Recipient Zip 62970-2331
Recipient Congressional District 12
Recipient Country USA
Required to Report Top 5
Highly Compensated Officials
Yes
Top 5 Officers and Compensation
Greg Therrien $1,103,425.00
Larry Farnes $604,563.00
Anthony J. Sandor $352,922.00
LeRoy Stromberg $928,305.00
Dave Kress $433,379.00

Projects and Jobs Information

Projects and Jobs Information
Project Title Federal Contract
Project Status Completed
Final Project Report Submitted Yes
Project Activities Description Other Heavy and Civil Engineering Construction
Quarterly Activities/Project Description This quarter, transfer of the LP-2 shell to water (Ohio River) was completed. The shell was set and grouted. Sill shell rebar protection was installed, and then removed when high water receded.
Jobs Created 6.43
Description of Jobs Created 6.43 FTEs were created or retained this quarter. 4.69 FTEs were Equipment Operators to support the shell setting and final operations. All other FTEs were working to support the final shell setting and sill shell rebar protection operations. These FTEs included the following: .64 FTE was an Ironworker; .32 FTE was an Electrician; .39 FTE was a Laborer; .32 FTE was a Piledriver; and .07 FTE was a Teamster. All are Heavy Construction Craft positions.


Purchaser Information (Contracts)

Purchaser Information
Contracting Office ID W912QR
Contracting Office Name Not Available
Contracting Office Region Not Available
TAS Major Program 96-3134

Award Information

Award Information
Award Date 09/03/2009
Award Number W912QR-04-C-0004
Order Number
Award Type Contracts
Funding Agency ID 96
Funding Agency Name Corps of Engineers
Funding Office Name Not Available
Awarding Agency ID 96
Awarding Agency Name Corps of Engineers
Amount of Award $27,941,413
Funds Invoiced/Received $27,941,413
Expenditure Amount $0
Infrastructure Expenditure Amount $0
Infrastructure Purpose and Rationale Not Reported
Infrastructure Point of Contact Name Not Reported
Infrastructure Point of Contact Email Not Reported
Infrastructure Point of Contact Phone Not Reported
Infrastructure Point of Contact Address Not Reported
Infrastructure Point of Contact City Not Reported
Infrastructure Point of Contact State Not Reported
Infrastructure Point of Contact Zip Not Reported

Product or Service Information (Contracts)

Product or Service Information
Primary Activity Code 237990
Activity Description Other Heavy and Civil Engineering Construction

Sub-Awards Information

Sub-Awards Information
Sub-awards to Organizations 29
Sub-award Amounts to Organizations $4,585,540
Sub-Awards to Individuals 0
Sub-Award Amounts to Individuals $0
Number of Sub-awards less than $25,000/award 576
Amount of Sub-awards less than $25,000/award $1,601,218
Number of payments to vendors greater than $25,000 0
Total Amount of payments to vendors greater than $25,000/award $0
Number of payments to vendors less than $25,000/award 0
Total Amount of payments to vendors less than $25,000/award $0


Sub-Award Transactions

Sub-award Hills-1 - Riechmann Transport, Inc.

Sub-Award Amount $29,317
Sub-Award Date 07/13/2010
Sub-Awards Disbursed $0.00
Project Location - City Granite City
Project Location - State IL
Project Location - Zip Code 62040-7000
Project Location - Congressional District 12
Sub-Recipient DUNS Number 186481313
Sub-Recipient Address 3328 W Chain of Rocks Rd
Sub-Recipient City Granite City
Sub-Recipient State Illinois
Sub-Recipient Zip Code 62040-7000
Sub-Recipient Congressional District 12
Required To Report Top 5
Highly Compensated Officials
No

Sub-award 50213891 - S & K ACQUISITION CORP

Sub-Award Amount $34,185
Sub-Award Date 10/12/2010
Sub-Awards Disbursed $0.00
Project Location - City Mattoon
Project Location - State IL
Project Location - Zip Code 61938-3462
Project Location - Congressional District 15
Sub-Recipient DUNS Number 005981642
Sub-Recipient Address 317 DEWITT AVE E
Sub-Recipient City MATTOON
Sub-Recipient State Illinois
Sub-Recipient Zip Code 61938-3462
Sub-Recipient Congressional District 15
Required To Report Top 5
Highly Compensated Officials
No

Sub-award 50203682 - SEFA GROUP, INC. THE

Sub-Award Amount $45,972
Sub-Award Date 10/01/2010
Sub-Awards Disbursed $0.00
Project Location - City Lexington
Project Location - State SC
Project Location - Zip Code 29073-8871
Project Location - Congressional District 02
Sub-Recipient DUNS Number 037219045
Sub-Recipient Address 217 CEDAR RD
Sub-Recipient City LEXINGTON
Sub-Recipient State South Carolina
Sub-Recipient Zip Code 29073-8871
Sub-Recipient Congressional District 02
Required To Report Top 5
Highly Compensated Officials
No

Sub-award 5024199 - SHAWNEE STONE, LLC

Sub-Award Amount $129,639
Sub-Award Date 11/21/2010
Sub-Awards Disbursed $0.00
Project Location - City Cypress
Project Location - State IL
Project Location - Zip Code 62923-2300
Project Location - Congressional District 19
Sub-Recipient DUNS Number 003040594
Sub-Recipient Address 202 W MAIN ST
Sub-Recipient City SALEM
Sub-Recipient State Illinois
Sub-Recipient Zip Code 62881-0001
Sub-Recipient Congressional District 19
Required To Report Top 5
Highly Compensated Officials
No

Sub-award 50213591 - Slsb, LLC

Sub-Award Amount $61,378
Sub-Award Date 09/21/2010
Sub-Awards Disbursed $0.00
Project Location - City Madison
Project Location - State IL
Project Location - Zip Code 62060-1083
Project Location - Congressional District 12
Sub-Recipient DUNS Number 141583927
Sub-Recipient Address 2000 Access Rd
Sub-Recipient City Madison
Sub-Recipient State Illinois
Sub-Recipient Zip Code 62060-1083
Sub-Recipient Congressional District 12
Required To Report Top 5
Highly Compensated Officials
No

Sub-award 50212679 - Slsb, LLC

Sub-Award Amount $51,021
Sub-Award Date 08/06/2010
Sub-Awards Disbursed $0.00
Project Location - City Madison
Project Location - State IL
Project Location - Zip Code 62060-1083
Project Location - Congressional District 12
Sub-Recipient DUNS Number 141583927
Sub-Recipient Address 2000 Access Rd
Sub-Recipient City Madison
Sub-Recipient State Illinois
Sub-Recipient Zip Code 62060-1083
Sub-Recipient Congressional District 12
Required To Report Top 5
Highly Compensated Officials
No

Sub-award 50211879 - STAR IRON WORKS, INC.

Sub-Award Amount $289,755
Sub-Award Date 05/19/2010
Sub-Awards Disbursed $0.00
Project Location - City Big Run
Project Location - State PA
Project Location - Zip Code 15715-0000
Project Location - Congressional District 05
Sub-Recipient DUNS Number 145696972
Sub-Recipient Address RD 3 BOX 155 MITCHELL AVE
Sub-Recipient City BIG RUN
Sub-Recipient State Pennsylvania
Sub-Recipient Zip Code 15715-8836
Sub-Recipient Congressional District 05
Required To Report Top 5
Highly Compensated Officials
No

Sub-award 50209517 - THE DYSON CORPORATION

Sub-Award Amount $51,135
Sub-Award Date 10/27/2009
Sub-Awards Disbursed $0.00
Project Location - City Painesville
Project Location - State OH
Project Location - Zip Code 44077-1232
Project Location - Congressional District 14
Sub-Recipient DUNS Number 796171163
Sub-Recipient Address 53 FREEDOM RD
Sub-Recipient City PAINESVILLE
Sub-Recipient State Ohio
Sub-Recipient Zip Code 44077-1232
Sub-Recipient Congressional District 14
Required To Report Top 5
Highly Compensated Officials
No

Sub-award 50216433 - Vernon L. Goedecke Company, Inc.

Sub-Award Amount $40,210
Sub-Award Date 06/16/2011
Sub-Awards Disbursed $0.00
Project Location - City Saint Louis
Project Location - State MO
Project Location - Zip Code 63110-1717
Project Location - Congressional District 01
Sub-Recipient DUNS Number 006327266
Sub-Recipient Address 4101 Clayton Ave
Sub-Recipient City Saint Louis
Sub-Recipient State Missouri
Sub-Recipient Zip Code 63110-1717
Sub-Recipient Congressional District 01
Required To Report Top 5
Highly Compensated Officials
No
<<<12>>>




Project Location Detail

Location Information
Latitude, Longitude 37º 11' 23", -89º 3' 59"
Congressional District 12
Address 1 675 New Dam Road
Address 2
City Olmsted
County Pulaski
State IL
Zip 62970-2316
Submit Feedback/Comments: Provide feedback or comments on the performance and progress of awards.