RJCL CORPORATION
This project consist of the installation of 207 meters of reinforced concrete open rectangular channel, 272 meters of underground reinforced concrete box channel, 368 meters of trapezoidal grassed waterway channel, 317 meters of temporary asphalt detour paving, 195 meters of coral road, 3 reinforced box culverts and other appurtenant such as grouted rock rip rap, chain link fencing, guaardrails and driveway crossing, with all materials, labor, and equipment inclusive. The total estimated quantity of reinforced concrete is 1710 cubic meters.