PEMBROKE TOWER, LTD.
1. Install water conservation devices:
100- (2.0gpm) shower heads
207- faucets(Allen Model #?s GK201, EL102N)(1.9gpm)
105-(1.28 gpf) ecodrake water closets(Mansfield model #EKTH15-135R)
101- single bowl stainless steel kitchen sinks(Dayton Brand)
106 - wall mount bathroom vanity sinks(Dayton Brand)
TOTAL $98,392.00
2. Replace existing 100 PTAC units with 100 Energy Star rated 15,000 btu Amana Brand PTAC units.
TOTAL $110,000.00
3. Replace existing 105 water heaters with 105 High Efficiency 30 gal. water heaters.(Rheem model #32V30-2 w/0.93 EF rating)
TOTAL : $62,500.00
4. Replace 132 existing windows with 132 Impact Resistant Energy Star assemblies. (0.24SHGC, 0.51 UF)
TOTAL : $104,400.00
5. Replace 95 existing Sliding glass door units with 95 Impact resistant Energy Star units (0.26SHGC, 0.58 UF).
TOTAL : $180,000.00
6. Replace 2 storefront door units with 2 Impact Resistant Energy Star Door Units (0.27 SHGC,0.6 UF).
TOTAL : $10,300.00
7. Replace 670 existing Edison-based light fixtures with 670 Energy Star fixtures and bulbs.(100 bathroom wall sconces in apt. units, 400 flush mount ceiling fixtures in apt. units, 100 patio wall sconces, and 70 ceiling fixtures in the hallways/ common areas)
TOTAL : $26,500.00
8. Replace existing cabinetry and countertops with ?Green? nonVOC cabinets and nonVOC countertops, (5 standard handicap units, 5 efficiency handicap units, 55 standard efficiency units, 35 standard units, and the common areas).
Kitchen Countertops :
Common Area Kitchen Cabinetry :
Common Area Kitchen Countertops :
TOTAL : $288,900.00
* Cabinets to be constructed of ?green? non-VOC 3/4 inch birch plywood boxes and 3/4 inch MDF door/drawer fronts (painted with white non-VOC primer and paint).
*Countertops to be ?green? non-VOC Particle board core with 1/16 inch plastic laminate top.
*120 degree self closing hinges, epoxy coated 3/4 extension bottom mount drawer slides, and satin chrome door/drawer handles included.
*All cabinets will be custom built to exactly match the existing cabinet footprint so that no modifications of cabinets or drywall will be needed.
9. Install an 8 Ton, 11.2 EER rooftop mounted ventilation system at existing location near the elevator shaft for corridors and hallways. Existing duct work will be utilized as it is in good working condition. All new electrical connections and crane used for installation included.
TOTAL : $68,000.00
10. Replace and dispose of 71 existing refrigerators with 71 Energy Star rated 15.5 cu.ft. GE brand refrigerators.
TOTAL : $43,500.00
11. Replace 8 existing exterior door units with 8 Impact Resistant Energy Star Door Units (0.24SHGC, 0.51 UF).
TOTAL : $16,900.00
12. Upgrade 2 elevators. Green modernization.
Total: $120,000
12. Replace roof with TPO Cool Roof System.
Total: $93,200