MASSACHUSETTS BAY TRANSPORTATION AUTHORITY
Invest in public transportation by providing the infrastructure necessary to extend Fitchburg Commuter Rail Line service 4.5 miles westward to a new station at Wachusett in West Fitchburg. The work includes track, bridge and signal improvements to the existing Pan Am Southern Freight Mainline between Fitchburg and Gardner; a new station at Wachusett; and a new train layover facility in Westminster. The initial grant award was $55,500,000; an additional $3,734,300 was approved for this project on 9/20/11 via Amendment #1 to the Grant Agreement.
Choose a quarter and click "Go."
| AWARD OVERVIEW |
| Award Number |
MA-78-0002 |
Funding Agency |
Department of Transportation |
| Total Award Amount |
$59,234,300 |
Project Location - City |
Fitchburg |
| Award Date |
11/09/2010 |
Project Location - State |
MA |
| Project Status |
Less Than 50% Completed |
Project Location - Zip |
01420-3155
|
| Jobs Reported |
8.80 |
Congressional District |
03 |
| Project Location - Country |
US |
|
|
Recipient Information
(Grants)
| Recipient Information (Grants) |
|
Recipient Name
|
MASSACHUSETTS BAY TRANSPORTATION AUTHORITY |
| Recipient DUNS Number |
122872260
|
| Recipient Address |
10 PARK PLZ STE 1 |
| Recipient City |
BOSTON |
| Recipient State |
Massachusetts |
| Recipient Zip |
02116-3975 |
| Recipient Congressional District |
07 |
| Recipient Country |
USA |
Required to Report Top 5 Highly Compensated Officials |
No |
Projects and Jobs Information
| Projects and Jobs Information |
| Project Title |
TIGER - Fitchburg Commuter Rail Line Extension and Wachusett Station |
| Project Status |
Less Than 50% Completed |
| Final Project Report Submitted |
No |
| Project Activities Description |
Mixed Mode Transit Systems |
| Quarterly Activities/Project Description |
This TIGER grant will allow the MBTA to extend the Fitchburg Commuter Rail Line an additional 4.5 milies westward of its current terminus, utilizing the existing Pan Am Southern railway corridor. The project will benefit both passenger rail service and freight operations, while reducing auto travel and providing more people with enhanced access to the Boston job market. The Early Action Site Preparation contract for the Station and Layover was awarded on 9/24/12 with NTP issued on 11/26/12. The Station and layover facility was advertised on 2/15/13; Bid opened on 4/2/13. Final design for track work was submitted on 3/6/13; Final design for signal work Phase 1 submitted on 12/21/12. Design of Signal Phase 2 is ongoing and is anticipated by late June 2013. Track and signal improvements will be performed by Pan Am Southern, the owner of the rail line, using materials procured by the MBTA. Initial track improvements began in August 2011. Material procurements for the remainder of the work is starting in spring 2013, with track and signal work resuming in the summer of 2013. Bridge ratings identified that significantly more bridge work is required than original estimates - 30% bridge design submitted on 3/14/13. The construction work for bridge repairs is anticipated in 2014. The project is scheduled to be substantially completed (start of revenue service to Wachusett Station) by the end of 2014. Project currently has a funding shortfall of $20.827 million; additional funding is being pursued including $5.51 million in repurposed earmarks. |
| Jobs Created |
8.80 |
| Description of Jobs Created |
As of 3/31/2013, the design is underway for the new Wachusett Station, Westminster Layover Facility and track work, and signal design. Track and signal improvements being performed by Pan Am Southern, the owner of the rail line, using materials procured by the MBTA. Initial construction work is underway, and will involve several trades. The MBTA will also procure track and signal materials for the project, providing manufacturing jobs in these industries. |
Purchaser Information
(Grants)
| Purchaser Information |
| Contracting Office ID |
Not Reported |
| Contracting Office Name |
Not Available |
| Contracting Office Region |
Not Available |
| TAS Major Program |
69-0106 |
| Award Information |
| Award Date |
11/09/2010 |
| Award Number |
MA-78-0002 |
| Order Number |
|
| Award Type |
Grants |
| Funding Agency ID |
69 |
| Funding Agency Name |
Department of Transportation |
| Funding Office Name |
Not Available |
| Awarding Agency ID |
69 |
| Awarding Agency Name |
Department of Transportation |
| Amount of Award |
$59,234,300 |
| Funds Invoiced/Received |
$8,640,639 |
| Expenditure Amount |
$8,994,072 |
| Infrastructure Expenditure Amount |
$8,994,072 |
| Infrastructure Purpose and Rationale |
This grant will be used to extend Fitchburg Commuter Rail Line service 4.5 miles westward to a new station at Wachusett; including track, bridge and signal improvements to the existing Pan Am Southern Freight Mainline between Fitchburg and Gardner, a new station at Wachusett, and a new train layover facility in Westminster. As such, this project will invest in transportation, environmental protection, and other infrastructure that will provide long-term economic benefits. The projects will also contribute toward creating jobs and promoting economic recovery. |
| Infrastructure Point of Contact Name |
Eric Waaramaa |
| Infrastructure Point of Contact Email |
ewaaramaa@mbta.com |
| Infrastructure Point of Contact Phone |
6172221950 |
| Infrastructure Point of Contact Address |
Ten Park Plaza |
| Infrastructure Point of Contact City |
Boston |
| Infrastructure Point of Contact State |
MA |
| Infrastructure Point of Contact Zip |
02116-3974 |
Product or Service Information
(Grants)
| Product or Service Information |
| Primary Activity Code |
485111 |
| Activity Description |
Mixed Mode Transit Systems |
| Sub-Awards Information |
| Sub-awards to Organizations |
0 |
| Sub-award Amounts to Organizations |
$0 |
| Sub-Awards to Individuals |
0 |
| Sub-Award Amounts to Individuals |
$0 |
| Number of Sub-awards less than $25,000/award |
0 |
| Amount of Sub-awards less than $25,000/award |
$0 |
| Number of payments to vendors greater than $25,000 |
9 |
| Total Amount of payments to vendors greater than $25,000/award |
$8,575,917 |
| Number of payments to vendors less than $25,000/award |
7 |
| Total Amount of payments to vendors less than $25,000/award |
$16,296 |
ARCADIS US , INC - Award Number MA-78-0002 - ARCADIS US , INC
| Award Number |
MA-78-0002 |
| Sub-Award Number |
N/A |
| Vendor DUNS Number |
Not reported |
| Vendor HQ Zip Code + 4 |
60693-0626 |
| Vendor Name |
ARCADIS US , INC |
| Product and Service Description |
Independent cost estimating services |
| Payment Amount |
$54,071 |
Hntb Corporation - Award Number MA-78-0002 - Hntb Corporation
| Award Number |
MA-78-0002 |
| Sub-Award Number |
N/A |
| Vendor DUNS Number |
083173091 |
| Vendor HQ Zip Code + 4 |
01803-4503 |
| Vendor Name |
Hntb Corporation |
| Product and Service Description |
Design and engineering services |
| Payment Amount |
$1,511,754 |
JACOBS ENGINEERING GROUP INC. - Award Number MA-78-0002 - JACOBS ENGINEERING GROUP INC.
| Award Number |
MA-78-0002 |
| Sub-Award Number |
N/A |
| Vendor DUNS Number |
809211936 |
| Vendor HQ Zip Code + 4 |
02210-1214 |
| Vendor Name |
JACOBS ENGINEERING GROUP INC. |
| Product and Service Description |
Design and engineering services |
| Payment Amount |
$2,265,384 |
MONTACHUSETT REGIONAL TRANSIT - Award Number MA-78-0002 - MONTACHUSETT REGIONAL TRANSIT
| Award Number |
MA-78-0002 |
| Sub-Award Number |
N/A |
| Vendor DUNS Number |
Not reported |
| Vendor HQ Zip Code + 4 |
01420-7266 |
| Vendor Name |
MONTACHUSETT REGIONAL TRANSIT |
| Product and Service Description |
Land acquisition, permitting and community outreach activities |
| Payment Amount |
$1,676,368 |
NCE VALUE CONSULTANTS INC - Award Number MA-78-0002 - NCE VALUE CONSULTANTS INC
| Award Number |
MA-78-0002 |
| Sub-Award Number |
N/A |
| Vendor DUNS Number |
Not reported |
| Vendor HQ Zip Code + 4 |
11530-1675 |
| Vendor Name |
NCE VALUE CONSULTANTS INC |
| Product and Service Description |
Value engineering services |
| Payment Amount |
$54,607 |
PAN AM SOUTHERN RAILWAY, LLC - Award Number MA-78-0002 - PAN AM SOUTHERN RAILWAY, LLC
| Award Number |
MA-78-0002 |
| Sub-Award Number |
N/A |
| Vendor DUNS Number |
Not reported |
| Vendor HQ Zip Code + 4 |
01862-1641 |
| Vendor Name |
PAN AM SOUTHERN RAILWAY, LLC |
| Product and Service Description |
Labor and equipment for installation of railroad ties |
| Payment Amount |
$1,016,800 |
S & R CONSTRUCTION CO INC DBA - Award Number MA-78-0002 - S & R CONSTRUCTION CO INC DBA
| Award Number |
MA-78-0002 |
| Sub-Award Number |
N/A |
| Vendor DUNS Number |
Not reported |
| Vendor HQ Zip Code + 4 |
03858-3711 |
| Vendor Name |
S & R CONSTRUCTION CO INC DBA |
| Product and Service Description |
Construction contractor |
| Payment Amount |
$1,534,795 |
TRAUNER CONSULTING SERVICES - Award Number MA-78-0002 - TRAUNER CONSULTING SERVICES
| Award Number |
MA-78-0002 |
| Sub-Award Number |
N/A |
| Vendor DUNS Number |
Not reported |
| Vendor HQ Zip Code + 4 |
19103-1807 |
| Vendor Name |
TRAUNER CONSULTING SERVICES |
| Product and Service Description |
Consulting services - risk analysis |
| Payment Amount |
$55,740 |
URS CORPORATION-NEW YORK - Award Number MA-78-0002 - URS CORPORATION-NEW YORK
| Award Number |
MA-78-0002 |
| Sub-Award Number |
N/A |
| Vendor DUNS Number |
Not reported |
| Vendor HQ Zip Code + 4 |
02110-3197 |
| Vendor Name |
URS CORPORATION-NEW YORK |
| Product and Service Description |
Project/construction management contractor |
| Payment Amount |
$406,397 |
| Location Information |
| Latitude, Longitude |
42º 35' 3",
-71º 48' 12" |
| Congressional District |
03 |
| Address 1 |
718 Main Street |
| Address 2 |
|
| City |
Fitchburg |
| County |
Worcester |
| State |
MA |
| Zip |
01420-3155 |
|
 |