ABENGOA BIOENERGY BIOMASS OF KANSAS, LLC
The project will fund approximately 300 construction jobs and 65 permanent jobs. The facility will convert approximately 300,000 tons of agricultural crop residues, including corn stover (stalks and leaves), into approximately 23 million gallons of ethanol per year using an innovative enzymatic hydrolisis process. The project maximizes the use of agricultural crop residues that would otherwise not be utilized and uses feedstock that does not compete with feed grains. Annually, the project is expected to displace over 15.5 million gallons of gasoline, which will avoid over 139,000 tons of carbon dioxide emissions. The facility will be self sufficient, using uncoverted biomass to generate 20 megawatts of electricity to power the cellulosic ethanol plant.
| AWARD OVERVIEW |
| Award Number |
LP0000055 |
Funding Agency |
Department of Energy |
| Total Award Amount |
$127,375,287 |
Project Location - City |
Hugoton |
| Award Date |
09/28/2011 |
Project Location - State |
KS |
| Project Status |
Less Than 50% Completed |
Project Location - Zip |
67951-0000
|
| Jobs Reported |
331.50 |
Congressional District |
01 |
| Project Location - Country |
US |
|
|
Recipient Information
(Loans)
| Recipient Information (Loans) |
|
Recipient Name
|
ABENGOA BIOENERGY BIOMASS OF KANSAS, LLC |
| Recipient DUNS Number |
782435874
|
| Recipient Address |
16150 MAIN CIR DR STE 300 |
| Recipient City |
CHESTERFIELD |
| Recipient State |
Missouri |
| Recipient Zip |
63017-4689 |
| Recipient Congressional District |
02 |
| Recipient Country |
USA |
Required to Report Top 5 Highly Compensated Officials |
No |
Projects and Jobs Information
| Projects and Jobs Information |
| Project Title |
Abengoa Bioenergy Biomass of Kansas |
| Project Status |
Less Than 50% Completed |
| Final Project Report Submitted |
No |
| Project Activities Description |
Energy Resources |
| Quarterly Activities/Project Description |
Commercial Tabulation of Equipment Bids Received.
Vendors Terms Negotiations.
RFQs Issuance.
Preparation of documents for construction of different areas: CIP, Chemicals, Mechanical Room, Ethanol Loadout, Stillage, Waste Treatment Plant, NG generators, Biomass Tower and Biomass Handling.
Electrical engineering still working on some of the areas, and also start issuing IFC documents for the contractors at the site.
Control System under development.
Foundations, tank installations, buildings erection, grounding, pipe racks installations, boiler construction, STG erection and Pre-Treatment area installation. |
| Jobs Created |
331.50 |
| Description of Jobs Created |
Civil Contractors |
Purchaser Information
(Loans)
| Purchaser Information |
| Contracting Office ID |
Not Reported |
| Contracting Office Name |
Not Available |
| Contracting Office Region |
Not Available |
| TAS Major Program |
89-4576 |
| Award Information |
| Award Date |
09/28/2011 |
| Award Number |
LP0000055 |
| Order Number |
|
| Award Type |
Loans |
| Funding Agency ID |
89 |
| Funding Agency Name |
Department of Energy |
| Funding Office Name |
Not Available |
| Awarding Agency ID |
89 |
| Awarding Agency Name |
Department of Energy |
| Amount of Award |
$127,375,287 |
| Funds Invoiced/Received |
$0 |
| Expenditure Amount |
$0 |
| Infrastructure Expenditure Amount |
$0 |
| Infrastructure Purpose and Rationale |
Not Reported |
| Infrastructure Point of Contact Name |
Not Reported |
| Infrastructure Point of Contact Email |
Not Reported |
| Infrastructure Point of Contact Phone |
Not Reported |
| Infrastructure Point of Contact Address |
Not Reported |
| Infrastructure Point of Contact City |
Not Reported |
| Infrastructure Point of Contact State |
Not Reported |
| Infrastructure Point of Contact Zip |
Not Reported |
Product or Service Information
(Loans)
| Product or Service Information |
| Primary Activity Code |
C05.02 |
| Activity Description |
Energy Resources |
| Sub-Awards Information |
| Sub-awards to Organizations |
0 |
| Sub-award Amounts to Organizations |
$0 |
| Sub-Awards to Individuals |
0 |
| Sub-Award Amounts to Individuals |
$0 |
| Number of Sub-awards less than $25,000/award |
0 |
| Amount of Sub-awards less than $25,000/award |
$0 |
| Number of payments to vendors greater than $25,000 |
0 |
| Total Amount of payments to vendors greater than $25,000/award |
$0 |
| Number of payments to vendors less than $25,000/award |
0 |
| Total Amount of payments to vendors less than $25,000/award |
$0 |
| Location Information |
| Latitude, Longitude |
37º 7' 5",
-101º 19' 22" |
| Congressional District |
01 |
| Address 1 |
Section 18, Township 33S |
| Address 2 |
Range 37W |
| City |
Hugoton |
| County |
Stevens |
| State |
KS |
| Zip |
67951-0000 |
|
 |