YAQUI ELECTRIC CO LLC
• Removal of the existing down to the deck insulation
• Remove the existing metal wall flashing and properly discard
• Mechanically attach on layer of 1/2" cover board to provide a smooth surface
• Mechanically attach one layer of 1/2" wood fiber cover board (45PSI)
• Mechanically attach 60mil TPO single ply material per the manufactures specifications
• TPO roofing material is to extend to the bottom edge of the existing coping metal
• Install new 24ga galvanized metal flashing under the existing coping metal, extending
• over the new TPO roofing material
• Install preformed pipe flashings where possible, field
• Install walk pads from roof access to the mechanical units
• Twenty-year manufactures warranty
• Two-year contractors warranty
PROJECT NUMBER 38801
PROJECT NUMBER 38786