Loans - AWARD SUMMARY


ARIZONA SOLAR ONE LLC


Abengoa Solar Inc.'s Solana project, will be the world's largest parabolic trough concentrating solar plant. Located near Gila Bend, Arizona, the 250-megawatt (MW) project is the first large-scale solar plant in the United States capable of storing energy it generates. Solana will produce enough energy to serve 70,000 households and will avoid the emissions of 475,000 tons of carbon dioxide per year compared to a natural gas burning power plant. Abengoa Solar Inc., the project sponsor, estimates that the Solana project will create between 1,600 to 1,700 new construction jobs and over 60 permanent jobs. The jobs created by the project will be located in Arizona and in neighboring states. To accommodate the project's need for over 900,000 mirrors, a mirror manufacturing facility will be built outside of Phoenix. As a result, the company anticipates the project will create additional direct investment in Arizona's economy.

Clarification of Codes

Choose a quarter and click "Go."


AWARD OVERVIEW

AWARD OVERVIEW
Award Number LP0000014 Funding Agency Department of Energy
Total Award Amount $1,359,082,586 Project Location - City Gila Bend
Award Date 12/21/2010 Project Location - State AZ
Project Status More than 50% Completed Project Location - Zip 85337-0000
Jobs Reported 1955.86 Congressional District 03
Project Location - Country US

Recipient Information (Loans)

Recipient Information (Loans)
Recipient Name ARIZONA SOLAR ONE LLC
Recipient DUNS Number 965442358
Recipient Address 4505 E CHANDLER BLVD STE 120
Recipient City PHOENIX
Recipient State Arizona
Recipient Zip 85048-0000
Recipient Congressional District 09
Recipient Country USA
Required to Report Top 5
Highly Compensated Officials
No

Projects and Jobs Information

Projects and Jobs Information
Project Title Solana Concentrating Solar Power Generating Station
Project Status More than 50% Completed
Final Project Report Submitted No
Project Activities Description Energy Resources
Quarterly Activities/Project Description At the end of this quarter the general schedule shows two important aspects: As per the end of February 2013 the little delay shown in January has not been recovered, although the EPC contractor has implemented a recovery plan. The risk of a delay is alive; In general, the project is progressing in accordance with the project budget, permits and regulations, and in a safe and secure manner. No violations in relation of permits and regulations have been recorded for this period. Provisional completion date slipped three additional days from the originally planned date due to a Force Majeure event in January 2013. New planning end date: July 26, 2013. No additional delays at the end of the project are expected at this stage. More than 1850 full time employees at the Solana site, including Labor, Management, Administration and Field Supervision. As of February the progress of the project is 94.4 %. Most relevant facts: 1. Solar field is complete. Installation of the tubes and head pipes that will carry on the Heat Transfer Fluid are complete; 2. HTF loop tests in the solar field in progress; 3. Salt started to be preheated in the salt tanks, and 2 tests have been performed; 4. General Contractor continues closing permits; 5. The filling of the tanks with Heat Transfer Fluid continues as planned; 6. NOx abatement system in place; 7. DCS programming continues in progress; 8. Mechanical works for the Thermal Energy Storage system in the Power Block progressing as planned; 9. Process water treatment system has been certificated by the County; 10. The bio-remediation pond and the evaporation ponds are fully operational; 11. All major deliveries are complete, except for balance of plant heat tracing & insulation; 12. O&M manuals, as build drawings, procedures and protocols in progress; 13. Zero environmental events and accidents having a material and adverse impact on the environment and human health.
Jobs Created 1955.86
Description of Jobs Created 1ST PERIOD ELECTRICAL APPRENTICE-55% (8); 2ND PERIOD ELECTRICAL APPRENTICE-60% (7); 3RD PERIOD ELECTRICAL APPRENTICE-65% (7); 4TH PERIOD ELECTRICAL APPRENTICE-70% (15); 5TH PERIOD ELECTRICAL APPRENTICE-80% (13); 6TH PERIOD ELECTRICAL APPRENTICE-90% (10); ASSEMBLERS USING RIVET GUNS (67) ; B&D ? 3RD YEAR ELECTRICIAN (1); B&D ? 5TH YEAR ELECTRICIAN (2); BOILERMAKER (3); CARPENTER (INCLUDING CEMENT FORM WORK) (103); CE2 CONSTRUCTION ELECTRICIAN (1); COLLECTOR ASSEMBLER (67); DRYWALL TAPER (1); ELECTRICIAN (347); FORK LIFT OPERATOR (74); INSULATOR (HEAT & FROST) (202); IRONWORKER (83); LABORER (653); LINE CONSTRUCTION (1); MECHANIC HEAVY DUTY (25); MILLWRIGHT (83); MILLWRIGHT APPRENTICE FIRST YEAR (1); OILER (8); OPERATOR ? TRACTORS (20); OWNER OPERATORS (9); PAINTER (2); PAINTER INDUSTRIAL (4); PAINTER INDUSTRIAL 60% (1); PAINTER-INDUSTRIAL 70% (2); PAINTER-INDUSTRIAL - APPRENTICE 80% (1); PARABOLIC TROUGH INSTALLATION SPECIALIST (166); PRABOLIC TROUGH INSTALLER (1); PIPEFITTER (642); PIPEFITTER 1ST YEAR (1); PIPEFITTER 2ND YEAR (1); PIPEFITTER 5TH YEAR (1); PLUMBER (180); PLUMBER APPRENTICE 1ST YEAR (16); PLUMBER APPRENTICE 2ND YEAR (4); PLUMBER APPRENTICE 3RD YEAR (2); PLUMBER APPRENTICE 56% (1); PLUMBER APPRENTICE 5TH YEAR (4); PLUMBER/PIPEFITTER (1); PLUMBER/PIPEFITTER APPRENTICE (26); POWER EQUIPMENT OPERATOR (140); QUALITY CONTROL PERSONNEL (66); ROLLER (1); SEMI-TRAILER TRUCK DRIVER (10); SHEET METAL WORKER (INCLUDING HVAC) (7); SPRINKLER FITTER (FIRE SPRINKLERS) (26); SPRINKLER FITTER (APPRENTICE ? CLASS 10) (1) ? SPRINKLER FITTER (APPRENTICE ? CLASS 9) (2); STEAMFITTER APPRENTICE-YEAR 4 (1); TOOL CRIB OPERATOR (4); TRUCK DRIVER (15); TECHNICIANS (SAMPLING , TESTING LABS) (5); SURVEY PERSONNEL (5); DIRECT SUPPORT (ENGINEERS, PM, OFFICE, FOREMEN) (945).


Purchaser Information (Loans)

Purchaser Information
Contracting Office ID Not Reported
Contracting Office Name Not Available
Contracting Office Region Not Available
TAS Major Program 89-4576

Award Information

Award Information
Award Date 12/21/2010
Award Number LP0000014
Order Number
Award Type Loans
Funding Agency ID 89
Funding Agency Name Department of Energy
Funding Office Name Not Available
Awarding Agency ID 89
Awarding Agency Name Department of Energy
Amount of Award $1,359,082,586
Funds Invoiced/Received $1,189,844,937
Expenditure Amount $1,189,844,937
Infrastructure Expenditure Amount $1,162,568,079
Infrastructure Purpose and Rationale Abengoa Solar Inc.'s Solana project will be the world's largest parabolic trough concentraing solar plant. Located near Gila Bend, Arizona, the 250-megawatt (MW) project is the first large-scale solar plant in the United States capable of storing energy it generates. Solana will produce energy to serve 70,000 households and will avoid the emissions of 475,000 tons of carbon dioxide per year compared to a natural gas burning power plant. Abengoa Solar Inc., the project sponsor, estimates that the Solana project will create between 1,600 to 1,700 new construction jobs and over 60 permanent jobs. The jobs created by the project will be located in Arizona and in neighboring states. To acommodate the project's need for over 90,000 mirrors, a mirror manufacturing facility will be built outside of Phoenix. As a result, the company anticipates the project will create additional direct investment in Arizona'a economy.
Infrastructure Point of Contact Name Emiliano Garcia Sanz
Infrastructure Point of Contact Email Emiliano.Garcia@solar.abengoa.com
Infrastructure Point of Contact Phone (303) 928-8500
Infrastructure Point of Contact Address 11500 West 13th Avenue
Infrastructure Point of Contact City Lakewood
Infrastructure Point of Contact State CO
Infrastructure Point of Contact Zip 80215-4406

Product or Service Information (Loans)

Product or Service Information
Primary Activity Code C05.02
Activity Description Energy Resources

Sub-Awards Information

Sub-Awards Information
Sub-awards to Organizations 0
Sub-award Amounts to Organizations $0
Sub-Awards to Individuals 0
Sub-Award Amounts to Individuals $0
Number of Sub-awards less than $25,000/award 0
Amount of Sub-awards less than $25,000/award $0
Number of payments to vendors greater than $25,000 1
Total Amount of payments to vendors greater than $25,000/award $1,162,568,079
Number of payments to vendors less than $25,000/award 0
Total Amount of payments to vendors less than $25,000/award $0




Vendor Transactions

Teyma USA & Abener Eng and Construction Services - Award Number LP0000014 - Teyma USA & Abener Eng and Construction Services

Award Number LP0000014
Sub-Award Number N/A
Vendor DUNS Number Not reported
Vendor HQ Zip Code + 4 85048-7686
Vendor Name Teyma USA & Abener Eng and Construction Services
Product and Service Description Design, engineer, procure, construct, startup and test a 280 MW (gross) concentrating solar power plant and 22 miles of a 230 kV Transmission Line, including the procurement of official authorizations, delivery of materials and spare parts.
Payment Amount $1,162,568,079



Project Location Detail

Location Information
Latitude, Longitude 32º 56' 51", -112º 44' 31"
Congressional District 03
Address 1 57750 S. Painted Rock Dam Road
Address 2
City Gila Bend
County Maricopa
State AZ
Zip 85337-0000
Submit Feedback/Comments: Provide feedback or comments on the performance and progress of awards.