| Other Awards |
Amount:
$558,702
Award Description: TAS::47 4543::TAS RECOVERY - CONSTRUCTION MANAGEMENT ASSIST SERVICES FOR FOLEY COURTHOUSE, SPOKANE WA. SERVICES INCLUDE PRE-DESIGN AND DESIGN PHASES FOR CMA, ENERGY MODELING/ENGINEERING AND COMMISSIONING |
Amount:
$25,365
Award Description: TAS::47 4543::TAS RECOVERY - CONSTRUCTION MANGEMENT ASSIST SERVICES FOR FOLEY COURTHOUSE, SPOKANE WA.
MODIFICATION TO ADD ARC FLASH COORDINATION STUDY. |
Amount:
$0
Award Description: TAS::47 4543::TAS RECOVERY - CONSTRUCTION MANGEMENT ASSIST SERVICES FOR FOLEY COURTHOUSE, SPOKANE WA. PRE-DESIGN AND DESIGN PHASE SERVICES - CORRECT FUND CITATION |
Amount:
$500,000
Award Description: TAS::47 4543::TAS ARRA-FUNDED MODIFICATION FOR DESIGN SUPPORT/UPDATE FINAL CONSTRUCITON DRAWINGS UNDER CM SUPPORT SERVICES FOR THE LAFAYETTE MODERNIZATION, 811 VERMONT AVENUE, NW, WASHINGTON, DC ARRA::YES::ARRA |
Amount:
$23,121
Award Description: TAS::47 4543::TAS
CONDUCT A STUDY THAT ANALYZES THE FEASIBILITY AND PROJECT IMIPACTS FOR SUPPORTING A POTENTIAL PRESIDENTIAL TRANSITION TEAM IN THE LAFAYETTE BUILDING DURING THE PHASE 1 MODERNIZATION PROJECT. |
Amount:
$0
Award Description: RECOVERY - CONSTRUCTION MANAGEMENT ASSIST (CMA) SERVICES FOR THE THOMAS S. FOLEY UNITED STATES FEDERAL COURTHOUSE MODERNIZATION PROJECT, SPOKANE, WASHINGTON
ADMINISTRATIVE MOD TO CORRECT LINE OF ACCOUNTING INFORMATION FROM MODIFICATION PO06. |
Amount:
$1,573,763
Award Description: RECOVERY - CMA SERVICES IN SUPPORT OF THOMAS S. FOLEY UNITED STATES FEDERAL COURTHOUSE, SPOKANE, WASHINGTON.
PO06 EXERCISES OPTIONS AND ADDS ADDITIONAL CMA SERVICES. |
Amount:
$15,832
Award Description: TAS::47 4543::TAS RECOVERY - CONSTRUCTION MANGEMENT ASSIST SERVICES FOR FOLEY COURTHOUSE, SPOKANE WA. PS05 TO ADD ADDITIONAL EPM TRAINING COSTS UNDER CLIN 0001. |
Amount:
$227,406
Award Description: RECOVERY - CMA SERVICES IN SUPPORT OF THOMAS S. FOLEY UNITED STATES FEDERAL COURTHOUSE, SPOKANE, WASHINGTON.
PO06 EXERCISES OPTIONS AND ADDS ADDITIONAL CMA SERVICES.
PS08 ADDS ADDITIONAL QUALITY ASSURANCE SERVICES IN SUPPORT OF CONSTRUCTION AND ASBESTOS ABATEMENT. |
Amount:
$39,028
Award Description: TAS::47 4543::TAS RECOVERY - CONSTRUCTION MANGEMENT ASSIST SERVICES FOR FOLEY COURTHOUSE, SPOKANE WA.
MODIFICATION TO CONVERT LEED N/C SERVICES TO LEED EB SERVICES. |
Amount:
$0
Award Description: TAS::47 4543::TAS RECOVERY - CONSTRUCTION MANGEMENT ASSIST SERVICES FOR FOLEY COURTHOUSE, SPOKANE WA. MOD PA04 CHANGES THE VENDOR'S DUNS NO. TO THE COORECT DUNS AND ALSO CHANGES THE ADDRESS AS A RESULT.
TAS::47 4543::TAS RECOVERY - CONSTRUCTION MANAGEMENT ASSIST SERVICES FOR FOLEY COURTHOUSE, SPOKANE WA. SERVICES INCLUDE PRE-DESIGN AND DESIGN PHASES FOR CMA, ENERGY MODELING/ENGINEERING AND COMMISSIONING |
Amount:
$60,339
Award Description: TAS::47 4543::TAS
ARRA - CONSTRUCTION MANAGEMENT ASSIST AND COMMISSIONING (CMA/CX) SERVICES FOR CONSTRUCTION PROJECT INVOLVING COOLING TOWER REPLACEMENT AND ENERGY CONSERVATION UPGRADES AT THE JAMES A. MCCLURE FEDERAL OFFICE BUILDING/U.S. COURTHOUSE IN BOISE, IDAHO. |
Amount:
$33,083
Award Description: "RECOVERY ACT" - CONTRACTOR TO PROVIDE COST ESTIMATING SUPPORT FOR THE FINAL CONSTRUCTION DOCUMENT SUBMISSION. |
Amount:
$25,589
Award Description: "RECOVERY ACT" - CONTRACTOR TO PROVIDE CONSTRUCTION MANAGEMENT SERVICES TO SUPPORT THE 95% CD RE-SUBMISSION. |
Amount:
$115,452
Award Description: REFERENCE: LAFAYETTE MODERNIZATION PROJECT - CM SERVICES
THE PURPOSE OF THIS MODIFICATION IS TO ADD ADDITIONAL CM SUPPORT DURING DESIGN. |
Amount:
$60,189
Award Description: REFERENCE: LAFAYETTE - CM SERVICES
THE PURPOSE OF THIS MODIFICATION IS TO ADD CM SUPPORT DURING 2-STEP PROCUREMENT. |
Amount:
$29,090
Award Description: THE PURPOSE OF THIS MODIFICATION IS TO ADD ADDITIONAL CONSTRUCTION MANAGEMENT SERVICES TO PROVIDE SUPPORT THROUGH FURNITURE/FURNISHINGS AND EQUIPMENT DESIGN FOR EXPORT-IMPORT BANK DURING THE DESIGN PERIOD. |
Amount:
$47,948
Award Description: RECOVERY: CONSTRUCTION MANAGEMENT ASSISTANT AND COMMISSIONING AUTHORITY (CMA/CX) SERVICES IN SUPPORT OF THE CHILLER REPLACEMENT AND ELEVATOR UPGRADE PROJECT AT THE YAKIMA FEDERAL BUILDING AND US COURTHOUSE IN YAKIMA WA |
Amount:
$60,750
Award Description: ARRA RECOVERY PROJECT - CONSTRUCTION MANAGEMENT ASSIST/COMMISSIONING (CMA/CX) SERVICES FOR THE COOLING TOWER REPLACEMENT AND ENERGY EFFICIENCY UPGRADES AT THE JAMES A. MCCLURE FEDERAL BUILDING/U.S. COURT HOUSE, BOISE, IDAHO. |
Amount:
$679,392
Award Description: RECOVERY ACT
TAS::47 4543::TAS
CONTRACT IS MODIFIED TO ADD SUPPLEMENTAL CM SERVICES FOR PHASE 1 CONSTRUCTION. |
Amount:
$21,234
Award Description: TAS::47 4543::TAS
CONTRACT IS MODIFIED TO ADD SURVEYING OF EXISTING FURNITURE AND FURNISHINGS IN EXIM, VA AND GSA SPACES WITHIN THE LAFAYETTE BUILDING. |
Amount:
$1,775,228
Award Description: TAS::47 4543::TAS
REFERENCE: LAFAYETTE MODERNIZATION PROJECT - CM SERVICES
THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE EQUITABLE ADJUSTMENT TO OPTION 1. |
Amount:
$2,050,338
Award Description: RECOVERY ACT
TAS::47 4543::TAS
REFERENCE: LAFAYETTE MODERNIZATION - HILL INTERNATIONAL (CM)
THE PURPOSE OF THIS MODIFICATION IS TO EXERCISE OPTION 1A AND 1B. |
Amount:
$2,443,996
Award Description: TAS::47 4543::TAS
REFERENCE: LAFAYETTE PROJECT - CM SERVICES
THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE ADDITIONAL STAFFING FOR PHASE 1 CONSTRUCTION MANAGEMENT SERVICES. |
Amount:
$243,390
Award Description: RECOVERY ACT
TAS::47 4543::TAS
CONTRACT IS MODIFIED TO ADD CM SUPPORT FOR LEAD AND ASBESTOS ABATEMENT DURING PHASE 1 CONSTRUCTION. |
Amount:
$1,806,086
Award Description: RECOVER ACT
TAS::47 4543::TAS
CONTRACT IS MODIFIED TO PROVIDE EQUITABLE ADJUSTMENT FOR OPTION 2. |
Amount:
$20,194
Award Description: TAS::47 4543::TAS
CONTRACT IS MODIFIED TO ADD PROJECT MANAGEMENT SUPPORT FOR THE SUB-DIVIDING OF PHASE 2 WORK OF THE CONSTRUCTION SOW. |
Amount:
$239,302
Award Description: RECOVERY ACT
TAS::47 4543::TAS
CONTRACT IS MODIFIED TO ADD SUPPLEMENTAL CM SERVICES TO PROVIDE EXIM SWING SPACE MOVE SERVICES. |
Amount:
$48,892
Award Description: TAS::47 4543::TAS
CONTRACT IS MODIFIED TO ADD PROJECT MANAGEMENT SUPPORT FOR THE IT/DATA AND TELECOM SERVICES TO SUPPORT EXIM'S SWING SPACE CONTRACTS. |
Amount:
$24,832
Award Description: RECOVERY - CONSTRUCTION MANAGEMENT AND COMMISSIONING SERVICES AT THE CURLEW BORDER STATION. |
Amount:
$170,000
Award Description: ADDITIONAL COMMISSIONING AGENT (CX) SERVICES |
Amount:
$120,430
Award Description: RECOVERY - CONSTRUCTION MANAGEMENT ASSIST SERVICES IN SUPPORT OF THOMAS S. FOLEY UNITED STATES FEDERAL COURTHOUSE DESIGN BUILD MODERNIZATION PROJECT. MODIFICATION PS09 ISSUED FOR ADDITIONAL DESIGN REVIEW EFFORTS |
Amount:
$13,542
Award Description: RECOVERY - CONSTRUCTION MANAGER ASSIST (CMA) SERVICES IN SUPPORT OF THOMAS S. FOLEY UNITED STATES FEDERAL COURTHOUSE DESIGN BUILD MODERNIZATION PROJECT, SPOKANE, WASHINGTON. MODIFICATION PS11 INCORPORATED TO PROVIDE ADDITIONAL CHANGE ORDER SUPPORT SERVICES. |
Amount:
$39,566
Award Description: RECOVERY - CONSTRUCTION MANAGER ASSIST (CMA) SERVICE IN SUPPORT OF DESIGN BUILD MODERNIZATION PROJECT AT THOMAS S. FOLEY UNITED STATES FEDERAL COURTHOUSE, SPOKANE, WA. PS10 ISSUED FOR ADDITIONAL CMA SERVICES. |
Amount:
$152,920
Award Description: ADDITIONAL ASBESTOS ABATEMENT MONITORING SERVICES |
Amount:
$50,580
Award Description: ARRA - CONSTRUCTION MANAGEMENT AND COMMISSIONING SERVICES FOR ENERGY EFFICIENCY MEASURES AT THE JAMES A. MCCLURE FEDERAL BUILDING/U.S. COURT HOUSE IN BOISE, IDAHO. EXTENSION REQUIRED TO TO DELAYS IN CONSTRUCTION. |
Amount:
$2,123
Award Description: COMMISSIONING TESTING |
Amount:
$5,757
Award Description: RECOVERY - EXTENSION OF CONTRACT COMPLETION DATE |
Amount:
$252,422
Award Description: RECOVERY ACT
TAS::47 4543::TAS
CONTRACT IS MODIFIED TO INCLUDE ADDITIONAL CONSTRUCTION MANAGEMENT SUPPORT FOR THE PHASE 1 AND PHASE 2 OF THE LAFAYETTE BUILDING MODERNIZATION PROJECT. |
Amount:
$0
Award Description: RECOVERY: CMA/CX SERVICES IN SUPPORT OF YAKIMA USCHSE&FED BLDG CHILLER AND ELEVATOR REPLACEMENT. THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE DUE TO ADDITIONAL EFFORT IN THE DESIGN PHASE OF THE CONSTRUCTION CONTRACT. |
Amount:
$6,484
Award Description: RECOVERY: CONTRACT MANAGEMENT ASSISTANT (CMA) AND COMMISSIONING AUTHORITY (CX) SERVICES IN SUPPORT OF THE CHILLER REPLACEMENT AND ELEVATOR UPGRADE AT THE YAKIMA FEDERAL BUILDING AND US COURTHOUSE. THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE. EXTENSION IS REQUIRED DUE TO EFFORTS TO BRING THE ELEVATOR SHAFT, FIRE ALARM AND ELEVATOR MACHINE ROOM INTO COMPLIANCE WITH LOCAL AND FEDERAL CODES BY THE CONSTRUCTION CONTRACT, CONTRACT NO: GS-10P-08-LT-D-0091/TASK ORDER NO.: GS-P-10-10-LT-5093. IN ADDITION, EXTENSION IS REQUIRED FOR COMMISSIONING OF THE CHILLED WATER SYSTEM WHICH IS SCHEDULED TO OCCUR AFTER THE COOLING SEASON AS WELL AS THE FOLLOW UP WARRANTY INSPECTION IN ACCORDANCE WITH THE STATEMENT OF WORK. |
Amount:
$100,000
Award Description: ADDITIONAL CM/CX SERVICES |
Amount:
$0
Award Description: ADDITIONAL CX SERVICES |
Amount:
$0
Award Description: ARRA - CONSTRUCTION MANAGEMENT AND COMMISSIONING SERVICES FOR ENERGY EFFICIENCY MEASURES AT THE JAMES A. MCCLURE FEDERAL BLDG/U.S. COURT HOUSE IN BOISE, IDAHO. EXTENSION REQUIRED TO PROVIDE TIME FOR 11TH MONTH WARRANTY INSPECTIONS AND APPLICABLE WARRANTY REPORTING. |
Amount:
$0
Award Description: DEFINITIZE PC36 - SCOPE OF WORK |