| Other Awards |
Amount:
$216,339
Award Description: TAS::12 1402::TAS RECOVERY - ARRS MAJOR RENOVATIONS TO WRRC - DESIGN UPDATES |
Amount:
$380,968
Award Description: TAS::12 1402::TAS
RECOVERY - ARCHITECT - ENGINEERING SERVICE TO UPDATE EXISTING DESIGN ARRA::YES::ARRA |
Amount:
$411,044
Award Description: TAS::28 0417::TAS.
CONSTRUCTION MANAGEMENT SERVICES FOR THE SOCIAL SECURITY ADMINISTRATION NEW NATIONAL SUPPORT CENTER, TO BE LOCATED IN THE VICINITY OF WOODLAWN, MARYLAND. THIS MODIFICATION IS FOR IT CONSULTING SERVICES: TASKS 2-4. |
Amount:
$46,338
Award Description: TAS::28 0417::TAS.
CONSTRUCTION MANAGEMENT SERVICES FOR THE SOCIAL SECURITY ADMINISTRATION NEW NATIONAL SUPPORT CENTER, TO BE LOCATED IN THE VICINITY OF WOODLAWN, MARYLAND. THIS MODIFICATION IS FOR TECHNICAL SUPPORT IN DEVELOPMENT OF SITE SELECTION CRITERIA AS WELL AS PROVIDE TECHNICAL ASSISTANCE IN SITE SELECTION AND EVALUATION. |
Amount:
$405,000
Award Description: TAS::28 0417::TAS. CONSTRUCTION MANAGEMENT SERVICES FOR THE SOCIAL SECURITY ADMINISTRATION NEW NATIONAL SUPPORT CENTER, TO BE LOCATED IN THE VICINITY OF WOODLAWN, MARYLAND. THIS MODIFICATION IS FOR IT CONSULTING SERVICES: IT EQUIPMENT GROWTH MODEL. ARRA::YES::ARRA |
Amount:
$43,711
Award Description: TAS::28 0417::TAS.
CONSTRUCTION MANAGEMENT SERVICES FOR THE SOCIAL SECURITY ADMINISTRATION NEW NATIONAL SUPPORT CENTER, TO BE LOCATED IN THE VICINITY OF WOODLAWN, MARYLAND. THIS MODIFICATION IS FOR COORDINATION, FACILITATION AND PARTICIPATION IN A TWO-DAY ENERGY CHARRETTE. |
Amount:
$788,036
Award Description: TAS::47 4543::TAS RECOVERY
REQUIREMENT FOR RE-COMMISSIONING/RETRO-COMMISSIONING SERVICES WHICH IS FUNDED BY THE AMERICAN RECOVERY AND REINVESTMENT ACT. |
Amount:
$6,493,366
Award Description: TAS::47 4543::TAS. - RECOVERY ACT MODIFICATION |
Amount:
$325,495
Award Description: TAS::47 4543::TAS. CONSTRUCTION MANAGER AS AGENT (CMA) SERVICES FOR THE HUNTINGTON FEDERAL BUILDING ENERGY REPAIR AND ALTERATIONS PROJECT, HUNTINGTON, WV. |
Amount:
$1,048,167
Award Description: CONSTRUCTION MANAGER AS AGENT FOR A WATER INTRUSION PROJECT IN TAMPA, FL: TAS::47 4543::TAS |
Amount:
$50,582
Award Description: TAS::47 4543::TAS RECOVERY
CONSTRUCTION MANAGER AS AGENT SERVICES FOR THE SPACE ALTERATION FOR 2 NEW 7TH FLOOR JUDGES CHAMBERS |
Amount:
$1,614,879
Award Description: TAS::12 1402::TAS -- CONSTRUCTION PHASE A&E SERVICES |
Amount:
$69,945
Award Description: TAS::12 1402::TAS RECOVERY - BID AND CONSTRUCTION PHASE A-E SERVICES |
Amount:
$85,000
Award Description: TAS::12 1402::TAS - ARRA - MAJOR RENOVATIONS TO WRRC |
Amount:
$104,930
Award Description: TAS::28 0417::TAS.
CONSTRUCTION MANAGEMENT SERVICES FOR THE SOCIAL SECURITY ADMINISTRATION NEW NATIONAL SUPPORT CENTER, TO BE LOCATED IN THE VICINITY OF WOODLAWN, MARYLAND. THIS MODIFICATION IS TO PROVIDE ADDITIONAL SITE SELECTION SUPPORT SERVICES. |
Amount:
$17,642
Award Description: CONSTRUCTION MANAGEMENT SERVICES, SOCIAL SECURITY ADMINISTRATION NATIONAL SUPPORT CENTER. THIS MODIFICATION IS TO PROVIDE A CONTAINMENT ANALYSIS FOR THE PROGRAM OF REQUIREMENTS. |
Amount:
$51,643
Award Description: CONSTRUCTION MANAGEMENT SERVICES, SSA NATIONAL SUPPORT CENTER
THIS MODIFICATION IS TO PROVIDE FOR IT CONSULTANT SUPPORT SERVICES DURING THE PROGRAM OF REQUIREMENTS, DESIGN/BUILD PROCUREMENT AND DESIGN DEVELOPMENT PHASES. |
Amount:
$299,956
Award Description: TAS::28 0417::TAS.
CONSTRUCTION MANAGEMENT SERVICES FOR THE SOCIAL SECURITY ADMINISTRATION NEW NATIONAL SUPPORT CENTER, TO BE LOCATED IN THE VICINITY OF WOODLAWN, MARYLAND. THIS MODIFICATION IS TO PROVIDE ADDITIONAL PROJECT MANAGEMENT SERVICES NECESSARY TO SUPPORT THE DEVELOPMENT OF AN ENHANCED PROGRAM OF REQUIREMENTS. |
Amount:
$177,588
Award Description: CONSTRUCTION MANAGEMENT SERVICES FOR THE SOCIAL SECURITY ADMINISTRATION NEW NATIONAL SUPPORT CENTER, TO BE LOCATED IN THE VICINITY OF WOODLAWN, MARYLAND. THIS MODIFICATION PROVIDES FOR ADDITIONAL SITE SELECTION SUPPORT SERVICES. |
Amount:
$1,132,353
Award Description: TAS::47 4543::TAS A-E SERVICES FOR WASHINGTON DC AREA |
Amount:
$0
Award Description: RECOVERY ADMINISTRATIVE MOD CORRECTS TOTAL AMOUNT |
Amount:
$252,024
Award Description: RECOVERY: PROVIDE COMMISSIONING SERVICES FOR THE MODERNIZATION OF THE MC SMITH FEDERAL BUILDING, BANGOR, MAINE. |
Amount:
$42,691
Award Description: RECOVERY:COMISSIONING AGENT AND CM SERVICES FOR MEP UPGRADE REPAIR AND ALTERATION PROJECT SAM M GIBBONS US COURTHOUSE TAMPA FL |
Amount:
$1,018,454
Award Description: RECOVERY COMMISSIONING AGENT AND CM SERVICES FOR MEP UPGRADE REPAIR NAD ALTERATION PROJECT SAM M. GIBBONS US COURTHOUSE TAMPA FLORIDA |
Amount:
$969,999
Award Description: RECOVERY: CONSTRUCTION MANAGER (CM) SERVICES FOR THE DETROIT FBI FIELD OFFICE CONSTRUCTION PROJECT IN DETROIT, MICHIGAN. PS05. |
Amount:
$389,400
Award Description: PROVIDE CONSERVATION SERVICES IN THE WHITE HOUSE VISITOR CENTER AND THE DEPARTMENT OF COMMERCE LAW LIBRARY |
Amount:
$459,085
Award Description: PROJECT MANAGER UNDER CONSTRUCTION MANAGEMENT SUPPLEMENTAL AND DELETE SUPPLEMENTAL SERVICES FOR ADMINISTRATIVE ASSISTANT |
Amount:
$0
Award Description: ADMINISTRATIVE MODIFICATION TO CHANGE CONTRACTOR NAME PER NOVATION AGREEEMENT. |
Amount:
$54,000
Award Description: ARRA:CMA SERVICES FOR LIGHTING REPLACEMENT AT FRANK M. SCARLETT FEDERAL BUILDING IN BRUNSWICK, GA. |
Amount:
$0
Award Description: THE PURPOSE OF THIS MODIFICATION IS TO CHANGE THE CONTRACTING OFFICER. |
Amount:
$0
Award Description: RECOVERY. CHANGE CONTRACTING OFFICERS |
Amount:
$150,000
Award Description: RECOVERY TAMPA SAM GIBBONS COURTHOUSE. JACOBS PROJECT MANAGEMENT SERVICES REQUIRED FOR MECHANICAL, ELECTRICAL, AND PLUMBING WORK BEING PERFORMED AT THE COURT HOUSE. |
Amount:
$764
Award Description: RECOVERY TAMPA SAM GIBBONS CMA CONTRACT. ATTEND MANDATORY EPM TRAINING. |
Amount:
-$7,365
Award Description: ARRA CONTRACT MODIFICATION TO DEFINITIZE ACTIONS AS STATED IN PC06 AS A RESULT OF DESING-BUILD CONTRACT EXTENSION AND INCREASE TO THAT SOW. |
Amount:
$317,113
Award Description: ADDITIONAL CMA SERVICES FOR ARRA NEW CUSTOM HOUSE MODERNIZATION PROJECT |
Amount:
$1,232,000
Award Description: -RECOVERY ACT MODIFICATION TO EXISTING CONTRACT- CM IS HEREBY TO PROVIDE ADDTL PROJECT MGR SUPPORT, ADDTL EST. SUPPORT, FINANCIAL CONTROLLER SUPPORT AND TESTING SERVICES ON A PDL BASIS. |
Amount:
$325,000
Award Description: MODIFICIATION IS FOR ADDITIONAL REQUIRED CMA SERVICES FOR THE CONSTRUCTION PROJECT. |
Amount:
$0
Award Description: DEFINITIZATION OF PREVIOUS UNILATERAL MODIFICATION. |
Amount:
$102,340
Award Description: MODIFICATION TO INCLUDE ADDITIONAL CMA SERVICES UNDER THE CESAR E. CHAVEZ MODERNIZATION PROJECT LOCATED IN DENVER, COLORADO |
Amount:
$65,485
Award Description: FEASIBILITY STUDY, PHASE 3A, WRRC, ALBANY, CA |
Amount:
$0
Award Description: -RECOVERY ACT MODIFICATION TO EXISTING CONTRACT-
NO-COST ADMINISTRATIVE MODIFICATION ISSUED TO ANCHOR ARRA FUNDS OBLIGATED UNDER PC19 FOR A CURRENT NEEDS FUND FOR ADDITIONAL PHASE 2/3 CONSTRUCTION MANAGEMENT SERVICES TO PROVIDE ADDITIONAL PROJECT MANGER SUPPORT, ADDITIONAL ESTIMATING SUPPORT, FINANCIAL CONTROLLER SUPPORT AND TESTING SERVICES ON A PRICE TO BE DETERMINED LATER (PDL) BASIS WHICH ESTABLISHED THE NOT-TO-EXCEED AMOUNT OF $1,232,000.
THIS ADMINISTRATIVE MODIFICATION DOES NOT REQUIRE ADDITIONAL CONTRACT FUNDS AS IT IS ISSUED TO CHARGE $441,969.00 OF THE $1,232,000.00 ARRA FUNDS ALLOCATED UNDER PC19 FOR THE FOLLOWING SERVICES: PROVIDE LEVEL A SUBGRADE TESTING SERVICES, PROVIDE A TIME EXTENSION FOR THE MEP COORDINATOR, PROVIDE 80 HOURS OF AUDIT SERVICES AND PROVIDE ADDITIONAL 3RD PARTY SCHEDULING AND CLAIM CONSULTING SERVICES. THEREFORE, THE CURRENT CONTRACT VALUE REMAINS UNCHANGED. |
Amount:
$0
Award Description: ALLOCATE FUNDS ISSUED UNDER MODIFICATION PS11 AND PA19 TO PROVIDE FOR ADDITIONAL CM STAFFING AND SUPPORT AS REQUESTED BY GSA FOR PHASE 2 AND 3
FINANCIAL MANAGER: $117,976.20 (PS11) NOTE: $210,219.08 WILL BE FUNDED VIA A SEPARATE MODIFICATION WITH RWA 80 FUNDS.
ESTIMATING SUPPORT SERVICES ON-SITE: $71,212.45 (PS11) NOTE: $53,137.80 WILL BE FUNDED VIA A SEPARATE MODIFICATION WITH RWA 80 FUNDS.
ASSISTANT PM SERVICES FROM 12/5/2011 THRU 9/7/2013: $377,039.60 (PS11) NOTE: $161,588 WILL BE FUNDED VIA A SEPARATE MODIFICATION WITH RWA 80 FUNDS.
PHASE 2&3 TIME EXTENSION OF 84 DAYS (7/30/2013 TO 9/7/2013): $204,526.00 (PS11) NOTE: $153,394.00 WILL BE FUNDED VIA A SEPARATE MODIFICATION WITH RWA 80 FUNDS.
ADDITIONAL INSPECTOR FOR ACCELERATION (JANUARY THRU MAY 2012): $79,094.00 (PS11) NOTE: $33,898.00 WILL BE FUNDED VIA A SEPARATE MODIFICATION WITH RWA 80 FUNDS.
ELECTRICAL INSPECTOR EXTENSION (2/7/2012 TO 4/30/2012: $4,251.43 (PS11), $46,268.57 (PS19)
ODCS FOR ADDITIONAL FINANCIAL MANAGER AND ESTIMATING: $2,650.94 (PS19) NOTE: $6,185.20 WILL BE FUNDED VIA A SEPARATE MODIFICATION WITH RWA 80 FUNDS.
ODCS FOR ADDITIONAL INSPECTORS: $4,200.00 (PS19) |
Amount:
$0
Award Description: MODIFICATION TO DEFINITIZE ADDITIONAL CMA SERVICES FOR THE CESAR E. CHAVEZ PROJECT LOCATED IN DENVER, COLORADO. |
Amount:
$32,195
Award Description: EQUITABLE ADJUSTMENT AGREEMENT FOR INCREASED PROJECT MANAGER TIME BETWEEN 10/2011 AND 3/2012. |
Amount:
$204,000
Award Description: ARRA FUNDED: CONSTRUCTION CONTRACT WAS EXTENDED DUE TO UNFORSEEN SITE CONDITIONS WHICH REQUIRED AN EXTENSION OF THE CM SERVICES CONTRACT |
Amount:
$137,417
Award Description: MODIFICATION TO EXTEND THE CMA SERVICES SUPPORTING THE ARRA CONSTRUCTION WORK FOR THE CESAR E. CHAVEZ MEMORIAL BUILDING LOCATED IN DENVER, COLORADO. |