| Other Awards |
Amount:
$1,913,046
Award Description: TAS::57 3744::TAS RECOVERY-CTGB082008-REPAIR FAMILY READINESS, BLDG 431
ARRA::YES::ARRA |
Amount:
$2,994,529
Award Description: TAS::57 3744::TAS - RECOVERY - YTPM053004 - REPAIR C-5 RAMP PERIMETER DRAINAGE, WESTOVER ARB, MA. THE COMPLETE REHABILITATION OF THE PERIMETER ROADWAY AND SERVICE APRONS BETWEEN THE EAST RAMP AND HANGARS 1, 3, 5, 7 AND 9. ARRA::YES::ARRA |
Amount:
$0
Award Description: TAS::57 3744::TAS RECOVERY-CTGB082008-REPAIR FAMILY READINESS, BLDG 431. ARRA::YES::ARRA |
Amount:
$0
Award Description: TAS::57 3744::TAS - RECOVERY - QJKL080018 - REPAIR AIRCRAFT PARKING APRON, REALIGN CLIN STRUCTURE PER DFAS ARRA::YES::ARRA |
Amount:
$1,315,808
Award Description: TAS::57 3744::TAS - RECOVERY - QJKL080018 REPAIR AIRCRAFT PARKING APRON - INCLUDING REMOVAL OF EXISTING DAMAGED AIRFIELD CONCRETE AND REINFORCEMENT, REPAIR AND REPLACEMENT OF CONCRETE AND OTHER MISC. REPAIRS AND MARKINGS FOR PROJECT QJKL 08-0018 ARRA::YES::ARRA |
Amount:
$77,496
Award Description: PROJECTNUMBER::38324RP# ARRA ARCHEOLOGICAL RE-EVALUATION STUDY SERVICE TO EVALUATE AND RE-VALIDATE ARCHEOLOGICAL SITES AND MAKE NRHP ELIGIBILITY RECOMMENDATIONS. |
Amount:
$218,189
Award Description: PROJECTNUMBER::38324RP# ARRA REPAIR TRAINING UNPAVED TANK TRAILS, VALIDATE ARCHEOLOGICAL DISTURBANCE AREAS ON FORT BLISS, EL PASO, TEXAS. |
Amount:
$45,793
Award Description: RECOVERYPROJECT#::38324::RP# ARRA REPAIR TRAINING UNPAVED TANK TRAILS, ARCHEOLOGICAL RE-EVALUATION SURVEY FOR FORT BLISS TANK TRAILS REPAIR PROJECT IN EL PASO TEXAS. |
Amount:
$413,125
Award Description: EXERCISE OPTION YEAR 1 - BILL AUDITING AND COMMODITY DATA ANALYSIS. |
Amount:
$24,111
Award Description: COMMODITY SERVICES MODIFICATION TO INCORPORATE THE PERFORMANCE WORK STATEMENT. |
Amount:
$1,259,672
Award Description: RECOVERY - ADVANCED MTERING SERVICES |
Amount:
$162,521
Award Description: RECOVERY ADVANCED METERING SYSTEM PHASE 2-INSTALLATION
MOD TO ADD THREE ADDITIONAL BLDGS |
Amount:
$0
Award Description: RECOVERY ADVANCED METERING SYSTEM PHASE 2-INSTALLATION
MOD PA01 - ISSUED TO CORRECT PROJECT NUMBERS FOR 3 LINE ITEM NOS.
TAS::47 4543::TAS |
Amount:
$0
Award Description: RECOVERY ADVANCED METERING SYSTEM PHASE 2-INSTALLATION
MOD PA02 ISSUED TO CORRECT BUILDING NUMBER FOR LINE ITEM 0039
TAS::47 4543::TAS |
Amount:
$3,503,352
Award Description: RECOVERY ADVANCED METERING SYSTEM PHASE 2-INSTALLATION
TAS::47 4543::TAS |
Amount:
$1,424,557
Award Description: TAS::57 3744::TAS RECOVERY-PDPG061201-REPLACE BLDG 600 HVAC |
Amount:
$0
Award Description: TAS::57 3744::TAS RECOVERY PDPG 06-1201, REPLACE BLDG 600 HVAC |
Amount:
$11,394
Award Description: TO ADD ONE ADDITOINAL ELECTRIC METER |
Amount:
-$247,189
Award Description: TO DELETE GAS AND WATER METERS FOR VARIOUS LOATIONS |
Amount:
$0
Award Description: RECOVERY
A. THIS MODIFICATION IS ISSUED AT THE REQUEST OF BUDGET TO CORRECT ORG CODE. THE ORG CODE IS CHANGED TO READ AS FOLLOWS:
PJ0D02823.2011.4421.04.PG03.P0440001.N40.PGH12.VGA00022.GA1007ZZ.150
B. ALL OTHER TERMS&CONDITIONS REMAIN UNCHANGED. |
Amount:
$83,590
Award Description: ARRA METERING ADDING 3 MORE GAS METERS AND 2 MORE WATER METERS AT THE HOWARD BAKER BLDG IN KNOXVILLE, TN |
Amount:
$34,502
Award Description: ADDITIONAL METERS TO BE INSTALLED TO THE CONTRACT |
Amount:
$5,241
Award Description: ADDING ADDITIONAL METERING FOR KEFAUVER FB |
Amount:
$247,189
Award Description: ADDING ONE ELECTRIC METER TO THE EXISTING CONTRACT |
Amount:
$0
Award Description: ADVANCED METERING INSTALLATIONS |
Amount:
$0
Award Description: RECOVERY - ADMINISTRATIVE MOD TO CHANGE CONTRACTING OFFICERS FROM BOBBIE CLARK TO WYLENE BELL |
Amount:
$0
Award Description: THIS IS AN ADMINISTRATIVE MOD TO CHANGE THE ACT # |
Amount:
$29,244
Award Description: TO ADD LOCAL RUNS TO THE CONTRACT |
Amount:
$36,976
Award Description: ADD LOCAL RUNS TO THE CONTRACT |
Amount:
$53,976
Award Description: RECOVERY:
TO PERFORM RECONFIGURATIONS FOR PIPING REQUIRED FOR METERING INSTALLATIONS AND TO INSTALL ELECTRIC METERS AT THE LOW BUILDING. |
Amount:
$8,333
Award Description: ADD ADDITIONAL METERS |
Amount:
$108,300
Award Description: ADD ADDITOINAL METERING TO THE CONTRACT FOR VARIOIUS BUILDINGS |
Amount:
$70,204
Award Description: RECOVERY. MODIFICATION TO INSTALL ELECTRICAL METERS AT SAM NUNN FEDERAL CENTER ATLANTA, GA. |
Amount:
$269,965
Award Description: TO PROVIDE ADDITIONAL METERS ( GAS, ELECTRIC, AND COOLING TOWERS) INSTALLTIONS FOR SPECIFIED BUILDINGS. ADDITIONS WERE ADDED DUE TO SITE VISIT FINDINGS. |
Amount:
$0
Award Description: THIS IS AN ADMINISTRATIVE MODIFICATION TO CHANGE BUILDING NUMBERS. |
Amount:
$113,566
Award Description: INCREASE SCOPE OF WORK WITH ADDITIONAL WORK |
Amount:
$324,414
Award Description: RECOVERY ADVANCED METERING SYSTEM PHASE 2-INSTALLATION
MODIFICATION ISSUED TO ADD ADDITIONAL METERS TO CONTRACT
TAS::47 4543::TAS
|
Amount:
$0
Award Description: MODIFICATION ISSUED TO EXTEND CONTRACT |
Amount:
$122,809
Award Description: RECOVERY ADVANCED METERING SYSTEM PHASE 2-INSTALLATION
MODIFICATION ISSUED ADD PV METERING AT THE EMMETT J. BEAN CTR., INDIANAPOLIS, IN.
TAS::47 4543::TAS |
Amount:
$0
Award Description: CONSTRUCTION SERVICES |
Amount:
$0
Award Description: RECOVERYPROJECT#::YTPM053004::RP#RECOVERY REPAIR C-5 RAMP PERIMETER DRAINAGE, WESTOVER ARB, MA. THE COMPLETE REHAVILITATION OF THE PERIMETER ROADWAY AND SERVICE APRONS |
Amount:
$0
Award Description: RECOVERYPROJECT#::YTPM053004::RP#RECOVERY REPAIR C-5 RAMP PERIMETER DRAINAGE, WESTOVER ARB, MA. THE COMPLETE REHABILITATION OF THE PERIMETER ROADWAY AND SERVICE APRONS |
Amount:
$0
Award Description: CONSTRUCTION SERVICES |
Amount:
-$63,614
Award Description: ARRA ADVANCED METERING SYSTEM - PHASE 2: INSTALLATION PROJECT. MODIFICATION PC13 WAS ISSUED TO ACCEPT THE CONTRACTOR'S PROPOSAL FOR A CREDIT FOR WORK OUTLINED IN MODIFICATION PC08. THE GOVERNMENT HAS DETERMINED THAT THE METERING WORK COULD BE COMPLETED THROUGH INTEGRATION OF THE METERING THROUGH THE BAS SYSTEM. THE CREDIT IS FOR $63,614.70; MODIFICATION PC08 WAS AWARDED FOR $122,809.41 AND MINUS THE CREDIT OF $63,614.70, THE NEW AWARD AMOUNT FOR MODIFICATION PC08 IS $59,194.71. |
Amount:
-$248,182
Award Description: TO DEOBLIGATE ARRA FUNDS FOR WORK NOT RECEIVED |
Amount:
$92,442
Award Description: THE PURPOSE OF THIS MODFICATION WAS TO INCORPORATE LOCAL RUNS REQUIRED TO COMPLETE THE PROJECT. |
Amount:
$25,652
Award Description: METERING PROJECTS R4 |
Amount:
-$31,615
Award Description: CONSTRUCTION SERVICES |