| Other Awards |
Amount:
$53,000,000
Award Description: TAS::47 4543::TAS RECOVERY ACT: THIS AWARD IS FOR THE FACADE AND SLATE ROOF REPAIR OF THE U.S. POST OFFICE & COURTHOUSE AT 271 CADMAN PLAZA EAST, BROOKLYN, NY. |
Amount:
$50,681
Award Description: TAS::47 4543::TAS : RECOVERY ACT. MODIFICATION PS06 TO CONTRACT GS02P07DTC0017 IS FOR INVESTIGATIVE PROBES TO BE DONE ON THE TOWER AND DORMERS, FOURTH FLOOR BAY, WALL CAVITIES, AND TOWER BALCONY. COSTS BASED ON ALLOWANCE 48 IN CONTRACT. |
Amount:
$0
Award Description: TAS::47 4543::TAS RECOVERY ACT: THE CONTRACT COMPLETION DATE HAS BEEN EXTENDED TO 08/20/2013. |
Amount:
$17,701
Award Description: TAS::47 4543::TAS RECOVERY ACT. THIS MODIFICATION IS TO FURNISH ALL EQUIPMENT, LABOR AND MATERIALS TO CUT A HOLE IN HTE ROOF, HOIST A BEAM TO THE ATTIC, INSTALL THE BEAM, MASONRY PATCHING, ROOF PATCHING AND ASSOCIATED PROTECTION AND CLEAN UP AS REQUIRED. |
Amount:
$0
Award Description: TAS:: 47 4543::TAS RECOVERY ACT: THIS MODIFICATION IS TO INCORPORATE THE REVISED SUBCONTRACTING PLAN INTO THE EXISTING CONTRACT. THE REVISED PLAN WAS APPROVED ON JULY 6, 2010. |
Amount:
$148,183
Award Description: TAS::47 4543::TAS RECOVERY ACT. THE ORGINAL CONTRACT HAS BEEN MODIFIED. THE MODIFICATION INCLUDES SECURITY CAMER ADJUSTMENTS WHERE THE VIEW IS OBSCURED DUE TO SCAFFOLDING. THE CONTRACT MUST WORK WITH THE USMS TO INSURE THAT THE USMS HAS A CLEAR VIEW OF THE BUILDING DURING ALL PHASES OF THE PROJECT. |
Amount:
$2,400,000
Award Description: TAS::47 4543::TAS RECOVERY ACT. THIS MODIFICATION HAS BEEN EXECUTED TO REPLACE THE TERRA COTTA ASHLARS AT THE PEIRS ON THE GPO AND BANKRUPTCY COURT. ALL UNIT PRICES WERE NEGOTIATED AT CONTRACT AWARD. |
Amount:
$14,946
Award Description: RECOVERY ACT: THIS IS A MODIFICATION TO THE CURRENT CONTRACT FOR THE 1892 BUILDING WINDOWS SCHEUDLE CLARIFICATION AND CONDENSATION DETAIL. |
Amount:
$189,658
Award Description: RECOVERY ACT: THIS MODIFICATION IS FOR THE 1892 BUILDING SLOT REPAIRS. THERE ARE APPROXIMATELY 90 WINDOWN OPENEINGS IN THE 1892 BUILDING. |
Amount:
$207,278
Award Description: TAS::47 4543::TAS RECOVERY ACT: REMOVE ASBESTOS CONTAINING MATIC AND CAULT. |
Amount:
$38,280
Award Description: RECOVERY ACT: TEMPORARY RELOCATION OF CONTENTS OF A TYPICAL USBC JUDGE'S CHAMBERS ON THE 2ND AND 3RD FLOORS IN THE 1892 AND 1933 BUILDING TO SWING SPACE LOCATED ON THE 2ND FLOOR OF THE 1892 BUILDING. |
Amount:
$221,277
Award Description: RECOVERY ACT: THE CURRENT CONTRACT HAS BEEN MODIFIED FOR THE TOWER BALCONY REPAIRS. INCLUDING: REMOVAL AND ABATEMENT OF EXISTING MATERIALS, REMOVE CONCRETE SLAB, REMOVE EXISTING PLASTER, RE-POINT ALL BRICK, REMOVE EXISTING STEEL, CHOP BEAM POCKETS, FURNISH AND INSTALL NEW DRAIN AND LEADER, AND FURNISH AND INSTALL NEW ROOFING MEMBRANE. |
Amount:
$101,920
Award Description: TAS::47 4543::TAS RECOVERY ACT. THIS MODIFICATION IS FOR THE CONTRACTOR TO INSTALL NEW SUBSTRATE FOR THE ENTIRE LENGTH OF THE 1892 UPPER AND LOWER GUTTERS. |
Amount:
$60,430
Award Description: RECOVERY ACT: THIS IS A MODIFICATION TO THE CURRENT CONTRACT TO INCLUDE AN UPDATED GRANITE REPAIR MATRIX BASED ON A FIELD SURVEY CONDUCTED ON JULY 10, 2010. |
Amount:
$164,582
Award Description: RECOVERY ACT: THIS IS A MODIFICATION TO THE EXISTING CONTRACT FOR TOWER MEZZANINE REPAIRS ON ADAMS STREET AND HOT THERMAL ZINC UPGRADE TO GRILLES AND CRESTING. |
Amount:
$532,613
Award Description: RECOVERY ACT: THIS MODIFICATION IS FOR THE GRANTIE DORMER REPAIRS ON THE 1892 BUILDING. |
Amount:
$26,511
Award Description: PROVIDE TOWER BALCONY GROUT ENGINEERING AND SUPERVISION. |
Amount:
$29,729
Award Description: STRUCTURAL REPAIR (MODIFICATION) AT THE ANGLES LOCATED AT THE ROOK EAVE OF THE TOWER OF THE GPO. |
Amount:
$170,039
Award Description: ADDITION OF PREMIUM TIME FOR STEEL PREPARATION AND INSTALLATION OF PLYWOOD PROTECTION. |
Amount:
$36,104
Award Description: 1892 BUILDING GRANITE REPAIRS. THIS IS DUE TO CHANGED CONDITIONS SINCE THE CONFORMED DRAWINGS WERE CREATED. THIS MODIFICATION ALSO INCLUDES A CREDIT FOR WINDOW WASHER BOLT REMOVAL. ALSO REPLACE THE MISSING BOLTS IN THE TOWER RAFTERS. |
Amount:
$172,188
Award Description: THIS MODIFICATION IS FOR THE LIGHTWELL FACADE AND STRUCTURAL REPAIRS ON THE 1892 BUILDING IN BROOKLYN, NY. |
Amount:
$175,921
Award Description: NEW GUTTER REVISIONS TO THE 1933 BUILDING BASED ON SITE OBSERVATIONS. |
Amount:
$393,885
Award Description: CONTRACTOR IS TO REBUILD THE DORMER LINTEL ON THE 1933 BUILDING IN BROOKLYN, NY |
Amount:
$602,257
Award Description: INCREASE IN WINDOW ALLOWANCES (IN BASE CONTRACT)IN ACCORDANCE WITH THE SCOPE OF WORK DATED FEBRUARY 28, 2011. |
Amount:
$297,000
Award Description: THIS MODIFICATION IS FOR THE EXTERIOR DOOR REPAIR AND REPLACEMENT OF THE BRONZE DOORS ALONG CADMAN PLAZA EAST AND THE WOOD DOORS ALONG JOHNSON STREET IN BROOKLYN, NY. |
Amount:
$17,890
Award Description: THIS MODIFICATION WAS ISSUED FOR FALL PROTECTION ON THE 1892 BUILDING TOWER. |
Amount:
$401,718
Award Description: REPLENISH CONTRACT ALLOWANCES THAT WERE IN THE BASE AWARD FOR GRANITE, MASONRY, AND REPAIR OF GRANITE. |
Amount:
$180,149
Award Description: FULL REPLACEMENT OF TWO TERRA COTTA BANDS ON THE 1933 BUILDING IN BROOKLYN, NY. |
Amount:
$226,908
Award Description: STRUCTURAL REPAIRS AT THE TOWER BALCONY LEVEL AND A DRAIN BODY CREDIT BACK TO GSA. |
Amount:
$30,835
Award Description: REPAIRS TO THE 1892 BUILDING INTERIOR WOOD STORM REPAIRS AND 100% WINDOW STOP REPLACEMENT. |
Amount:
$93,507
Award Description: REPLENISH ALLOWANCES A6, A38, A39, A42, A43 AND A46. |
Amount:
$55,383
Award Description: FURNISH AND INSTALL INTERIOR METAL WINDOW SLOPES AT THE LOWER OPERABLE SASH AT THE INTERIOR OF THE 1892 BUILDING. |
Amount:
$335,479
Award Description: PROVIDE STORM WINDOW HARDWARE ALLOWANCES |
Amount:
$160,255
Award Description: 1892 BUILDING CHIMNEY CAP REVISIONS INCLUDING REPAIR, REPLACEMENT OF BRICK AS WELL AS ANCHORING A NEW CHIMNEY CAP. |
Amount:
$251,447
Award Description: THIS MODIFICATION IS FOR COPPER GUTTER INSTALLATION AND STEEL COATING SUBSTITUTION ON THE 1933 BUILDING IN BROOKLYN, NY. IT IS ALSO FOR THE 1892 BUIDLING NEW CHIMNEY CAP FLASHING TO BE INSTALLED. |
Amount:
$929,815
Award Description: THIS MODIFICATION IS FOR TERRA COTTA ASHLAR BLOCKS AND DECORATIVE TERRA COTTA STONES TO BE REPLACED ON TILLARY STREET AND SADMAN PLAZA EAST. ALSO, (40) UNITES ARE TO BE REPLACED ON THE 2ND FLOOR ON ADAMS STREET. |
Amount:
$12,255
Award Description: THIS MODIFICATION IS FOR REVISED GRANITE DORMER REPAIRS WITHIN THE LIGHTWELL ON THE 1892 BUIDING. |
Amount:
$0
Award Description: THIS MODIFICATION IS FOR: ADDITIONAL INJECTION GROUT AT THE 1892 BALCONY LEVEL BEAM POCKETS, PRIMING OF COPPER FLASHING AT WINDOW SILLS AND REFINISHING OF STEEL ANGLE AT WINDOW SASHES, LIGHTWELL ROOF END WORK AND DOWNSPOUNT INSTALLATION AND OUTRIGGER AND CLIP ANGLE REPAIRS. |
Amount:
$0
Award Description: THIS MODIFICATION IS A $0 DOLLAR MODIFICATION FOR SECURITY WORK ON BRONZE DOORS COUPLED WITH REVISED BRONZE DOOR ENTRY DOOR HARDWARE. THIS IS A ZERO DOLLAR MOD BECAUSE THE CONTRACTOR GAVE A CREDIT FOR UTILITIES. |
Amount:
$0
Award Description: THIS MODIFICATION IS TO DELETED ALLOWANCES TO REBUILD GANITE AND CREATED AN ALLOWANCE FOR SCALING BACK EXISTING GRANITE |
Amount:
$0
Award Description: THIS MODIFICATION IS FOR HTE REALLOCATION OF ALLOWANCES AND SNOWPADS TO BE INSTALLED ON THE 1892 BUILDING CHIMNEY CAP AND FOR REPAIRS TO THE DECORATIVE TERRA COTTA SPANDRELS. |
Amount:
$0
Award Description: ADDITIONAL ALLOWANCE AND CREDIT FOR US ATTORNEY SPACE IMPROVEMENTS |
Amount:
$0
Award Description: THIS MODIFICATION WAS FOR A CHANGE IN SIZE OF THE LOWER GUTTERS. THIS IS A $0 MODIFICATION. |
Amount:
-$1,523
Award Description: THIS MODIFICATION IS FOR THE FOLLOWING: REVISED DORMERS, REVISED JOINT CONTROL JOINTS, REPLACEMENT OF REMAINING 1933 BUILDING WINDOWN SASHES AND A CREDIT FOR ALLOWANCES, ADDITIONAL PREMIUM TIME FOR WORK AT THE 1933 BUILDING, AND 1933 TILLARY STREET OUTRIGGER AND CLIP ANGLE CREDITS AND REPAIRS. |