| Other Awards |
Amount:
$12,650
Award Description: DESIGN CHANGE FOR THE ROOFING PROJECT AT ALLIANCE TOWER, HOUSTON, TX |
Amount:
$41,444
Award Description: RESTORE WINDOWS IN ELEVATOR PENTHOUSE, CUSTOMS HOUSE, HOUSTON, TX |
Amount:
$242,208
Award Description: EXERCISE OPTION 2, BOB CASEY CH, HOUSTON, TX |
Amount:
$1,026,773
Award Description: EXERCISED OPTION 1, ROOF RENOVATION, ALLIANCE TOWER, HOUSTON, TX |
Amount:
$0
Award Description: CORRECT ACCOUNTING CODES |
Amount:
$1,055,820
Award Description: EXERCISED OPTION 3, LABRANCH FB, HOUSTON, TX |
Amount:
$1,359,378
Award Description: ARRA ROOF AND EXTERIOR RENOVATION, U.S. CUSTOMS HOUSE 701 SAN JACINTO STREET, HOUSTON, TX |
Amount:
$0
Award Description: CHANGE CODING |
Amount:
$2,434,661
Award Description: ARRA ROOF REPLACEMENT AND EXTERIOR RESTORATION AT THE ABUQUERQUE, NM FEDERAL BUILDING. |
Amount:
$1,884,517
Award Description: REPLACE ROOF AND RENOVATE EXTERIOR OF A. MACEO SMITH FEDERAL BUILDING IN DALLAS, TEXAS. ARRA FUNDED PROJECT |
Amount:
$0
Award Description: CORRECTION OF LINE PROBLEM ON MODIFICATION PS04. NO COST. |
Amount:
$11,903
Award Description: MODIFICATION TO UPGRADING ROOF MEMBRANE ON MAHON FB. |
Amount:
$0
Award Description: CORRECTION OF FUNCTION CODE FOR ALL ACCOUNTING LINES, PER BUDGET FOR 7PF. NO COST. |
Amount:
$0
Award Description: MOD TO ADD ARRA CLAUSES FOR PAYMENT PROCEDURES. REPLACE ROOF FOR G. MAHON FEDERAL COURTHOUSE/POST OFFICE, MIDLAND, TEXAS (ARRA PROJECT) |
Amount:
$2,067,396
Award Description: TAS::47 4543::TAS, RECOVERY WORK. REPLACE ROOF FOR GEOGRE MAHON COURTHOUSE/POST OFFICE, 100 -200 WALL STREET, MIDLAND, TEXAS. (ARRA PROJECT) |
Amount:
$3,154
Award Description: ADD AFTER HOUR AND WEEKEND FIRE ALARM SERVICES FOR LB&B. |
Amount:
$0
Award Description: TAS::47 4543::TAS, RECOVERY WORK. REPLACE ROOF FOR G. MAHON FEDERAL COURTHOUSE/POST OFFICE, MIDLAND, TEXAS (ARRA PROJECT) |
Amount:
-$1,660
Award Description: MOD TO DEOBLIGATE UNUSED FUNDS FOR FIRE ALARM MONITORING AT ROOF REPLACEMENT AT G. MAHON FEDERAL BUILDING/COURTHOUSE AND MAINTENANCE BUILDING IN MIDLAND, TEXAS. (ARRA PROJECT) |
Amount:
$165,491
Award Description: LABRANCH FEDERAL BUILDING, HOUSTON, TX, ROOF DECK WAS IN WORSE CONDITION THAN ANTICIPATED. THIS MOD WILL RENOVATE THE DECK. |
Amount:
-$91,584
Award Description: ARRA ROOFING PROJECT, HOUSTON, TX DELETE LINE ITEM 0024 FROM PS09 |
Amount:
$365,967
Award Description: MODIFICATION PS08 WILL REPLACE THE DETERIORATED INSULATED WINDOW PANES AT THE CUSTOMS HOUSE, HOUSTON, TX |
Amount:
$5,250
Award Description: REPLACEMENT OF LADDER AND WALK PAD AT BASE OF LADDER AT MACEO FEDERAL BUILDING IN DALLAS, TEXAS. ARRA FUNDED PROJECT |
Amount:
$0
Award Description: TO CORRECT ACCOUNTING AND APPROPRIATION DATA |
Amount:
$140,121
Award Description: ADDITIONAL WORK WITHIN SCOPE |
Amount:
$37,480
Award Description: ADDITIONAL WORK WITHIN SCOPE FOR SPALL AND WINDOW REPAIR |
Amount:
$100,000
Award Description: TO DEFINITIZE MOD PC03 AND ADDITIONAL WORK |
Amount:
$17,187
Award Description: ADDITIONAL WORK WITHIN SCOPE |
Amount:
$77,808
Award Description: THE AFOREMENTIONED DELIVERY ORDER IS CHANGED TO INCLUDE ADDITIONAL WORK WITHIN SCOPE OF CONTRACT. |
Amount:
$1,824,195
Award Description: THIS IS AN ADMINISTRATIVE MODIFICATION TO CORRECT FPDS-NG REPORTING REQUIREMENTS BY CHANGING PORTION OF LINE ITEM 0001 ($1,824,195.00) FROM BA54 FUNDS TO BA 03 FUNDS. |
Amount:
$52,965
Award Description: REVISE THE METHODS/MATERIALS ASSOCIATED WITH THE INSTALLATION OF THE TILE ROOF SYSTEM PER THE SCOPE OF WORK. |
Amount:
$0
Award Description: TO CORRECT BUILDING NUMBER IN ACC&APP DATA |
Amount:
$0
Award Description: TO CORRECT CONTRACTING OFFICER IN C.SUITE |
Amount:
$0
Award Description: COMPLETION DATE IS EXTENDED TO JANUARY 31, 2012, DUE TO THIS CHANGE. THIS EXTENSION IS GRANTED AT NO ADDITIONAL COST TO THE GOVERNMENT OR CONTRACTOR. |