| Other Awards |
Amount:
$339,831
Award Description: TAS::47 4543::TAS RECOVERY PROJECT
PROVIDE RETRO-COMMISSIONING SERVICES FOR THREE FEDERAL BUILDINGS. |
Amount:
$0
Award Description: TAS::47 4543::TAS RECOVERY PROJECT
ADMINISTRATIVE MODIFICATION TO CORRECT PROJECT NUMBER.
PROJECT IS TO PROVIDE RETRO-COMMISSIONING STUDIES FOR THREE BUILDINGS. |
Amount:
$169,968
Award Description: RECOVERY - TAS::47 4543::TAS
RE-COMMISSIONING/RETRO-COMMISSIONING FOR EAGLETON COURTHOUSE AND NORTH PLATTE FEDERAL BUILDING. |
Amount:
$72,576
Award Description: RECOVERY - TAS::47 4543::TAS
MODIFICATION TO INCORPORATE ENERGY MANAGEMENT CONTROL SYSTEM AND ADVANCED METERING SERVICES INTO TASK ORDER FOR EAGLETONA AND NORTH PLATTE FEDERAL BUILDING ARRA::YES::ARRA |
Amount:
$128,935
Award Description: RECOVERY - TAS::47 4543::TAS
RETRO-COMMISSIONING FOR ROBERT DENNEY BUILDING ONLY AND ENERGY MANAGEMENT CONTROL SYSTEM SERVICES WITH ADVANCED METERING FOR THE DENNEY FEDERAL BUILDING, ZORINSKY FEDERAL BUILDING, AND DAVENPORT U.S. COURTHOUSE AND FEDERAL BUILDING |
Amount:
$455,649
Award Description: TAS::47 4543::TAS RECOVERY
TUNE-UP RECOMMISSIONING |
Amount:
$446,012
Award Description: TAS::47 4543::TAS - RECOVERY ACT -
COMMISIONING AGENT SERVICES |
Amount:
$50,609
Award Description: TAS::13 1454::TAS
RECOVERY FUNDS- COMMISSIONING SERVICES FOR AQUA CEL BUILDING, GALVESTON, TEXAS |
Amount:
$0
Award Description: TAS::47 4543::TAS RECOVERY
REVISE COMPLETION DATE |
Amount:
-$64,524
Award Description: TAS::47 4543::TAS RECOVERY PROJECT
PROVIDE RETRO-COMMISSIONING SERVICES FOR THREE FEDERAL BUILDINGS. |
Amount:
$12,500
Award Description: "RECOVERY" TO PROVIDE DESIGN-BUILD SUPPORT SERVICES FOR VARIOUS BUILDINGS IDENTIFIED IN THE SCOPE OF WORK |
Amount:
$1,459,950
Award Description: RECOVERY - ENERGY MANAGEMENT CONTROL SYSTEM UPGRADES AND ADVANCED UTILITY METERING FOR VARIOUS BUILDINGS WITH GSA REGION 6 |
Amount:
$534,725
Award Description: TAS::97-0501::TAS RECOVERY PROJECT#69693
ARRA- MOTION LIGHT SENSING SWITCHES
|
Amount:
$0
Award Description: RECOVERY. CHANGE CONTRACTING OFFICERS FROM LESLIE SMALLS TO BOBBIE CLARK |
Amount:
$39,181
Award Description: RECOVERY. EXTEND COMMISSIONING AND LEED SERVICES FURING CONSTRUCTION INCLUDING PROJECT CLOSEOUT. |
Amount:
$16,990
Award Description: RECOVERY :: 47 4543
CHILLED WATER LOOP INVESTIGATION
THOMAS F. EAGLETON U.S. COURTHOUSE, ST. LOUIS, MO |
Amount:
$0
Award Description: TO DEOBLIGATE REMAINING FUNDS (.02) AND REVISE PERFORMANCE PERIOD. |
Amount:
-$3,486
Award Description: DE-OBLIGATION OF EXCESS FUNDS SINCE THE ZORINSKY PROJECT WILL NOT PROCEED FURTHER. |
Amount:
$34,248
Award Description: ADDITIONAL WORK FOR CABLING |
Amount:
$220,307
Award Description: TAS ::47 4543
ADDITIONAL METERING WORK |
Amount:
$0
Award Description: CHANGE FUNDING STRINGS PER CENTRAL OFFICE REQUEST |
Amount:
$46,045
Award Description: ENERGY CONSERVATION |
Amount:
$0
Award Description: THE IS A ADMIN MOD TO AN ARRA CONTRACT TO EXTEND THE TIME FOR PROPER COMPLETION OF THE PROJECT. |
Amount:
$0
Award Description: ADMINISTRATIVE MODIFICATION |
Amount:
$0
Award Description: ARRA RE-COMMISSIONING SUPPORT SERVICES
THIS EXTEND THE LIFE OF THE CONTRACT TO SUPPORT THE CONSTRUCTION CONTACT ISSUED TO WINDAMIR TO COMPLETE THEIR PORTION OF THE WORK. |
Amount:
$0
Award Description: OT - ADMINISTRATIVE MODIFICATION TO UPDATE COMPRIZONSUITE TO REFLECT CHANGES MADE IS PS06. |
Amount:
$0
Award Description: OT - RECOVERY - EXTEND THE TERMS OF THE CONTRACT TO ALLOW COMMISSIONING AGENT TO COMPLETE CONTRACTED WORK. DELAY IS DUE TO GENERAL CONTRACTOR LATE COMPLETION OF PROJECT - MCCOY FEDERAL BUILDING |