| Other Awards |
Amount:
$3,048,318
Award Description: TAS::47 4543::TAS. - RECOVERY ACT - EXERCISE OF OPTION 9 - A/E POST CONSTRUCTION CONTRACT SERVICES FOR PHASE 2 AND PHASE 3 OF THE DEPARTMENT OF COMMERCE RENOVATION PROJECT |
Amount:
$180,992
Award Description: TAS::47 4543::TAS. - RECOVERY ACT - CONTRACTOR TO PROVIDE ADDITIONAL ARCHITECTURAL, ENGINEERING AND COST ESTIMATING SERVICES TO STUDY THE FEASIBILITY OF INSTALLING FUEL CELLS AT HCHB |
Amount:
$1,757
Award Description: -RECOVERY ACT MODIFICATION- PS52 IS TO PROVIDE FUNDS FOR LABOR RATE ESCALATION COVERING THE PERIOD OF NOV 30, 2009 TO NOV 29, 2010. |
Amount:
$0
Award Description: THIS IS AN ADMINISTRATIVE MOD CORRECTING PS52. |
Amount:
$51,011
Award Description: PROVIDE ADDITIONAL LEED SERVICES FOR PHASE 2 AND PHASE 3, PER THE ATTACHED SCOPE OF WORK. |
Amount:
$58,612
Award Description: TAS::47 4543::TAS. - PROVIDE A/E SERVICES TO REDESIGN THE STRUCTURAL REQUIREMENTS AT TWO LOCATIONS IN CY1 TO SUPPORT PROPOSED FUEL CELLS, PER THE ATTACHED SCOPE OF WORK.
|
Amount:
$46,910
Award Description: ARRA FUNDED MODIFICATION - PROVIDE SUB CONSULTANT CA SERVICES TO PHASE 2 |
Amount:
$75,381
Award Description: CONTRACTOR TO PROVIDE ADDITIONAL ARCHITECTURAL, ENGINEERING AND COST ESTIMATING SERVICES TO DESIGN A STORM WATER STORAGE CISTERN IN THE BASEMENT OF COMMERCE, PER THE ATTACHED SCOPE OF WORK.
|
Amount:
$27,039
Award Description: ADDITIONAL SERVICES TO AMEND ENVIRONMENTAL ASSESEMENT |
Amount:
-$313,856
Award Description: DEOBLIGATION OF CLIN 0100 OF MODIFICATION PC77 FOR WORK RELATING TO PROVIDING ADDITIONAL PCCS SERVICES AND CLIN 0101 OF MODIFICATION PC77 FOR WORK RELATING TO PHASE 2 RECORD DRAWINGS. |
Amount:
$12,166
Award Description: RECOVERY ACT MODIFICATION TO EXISTING CONTRACT
THIS MODIFICATION PROVIDES ADDITIONAL CONSTRUCTION ADMINISTRATIVE SERVICES TO PROVIDE BLAST ANALYSIS REVIEW OF THERMOLITE WINDOWS FOR HCHB AND ADDITIONAL CA SERVICES USING HINMAN, THE BLAST CONSULTANT. |
Amount:
$500,000
Award Description: PRICE-TO-BE-DETERMINED-LATER BASIS: PROVIDE ADDITIONAL ARCHITECTURAL AND ENGINEERING SERVICES FOR ADDITIONAL PCCS SERVICES FOR PHASE 2, EXTENDING TO MARCH 16, 2012 AND FOR THE PREPARATION OF PHASE 2 AND PHASE 3 RECORD DRAWINGS, PER OPTION 10 OF THE CONTRACT. |
Amount:
$12,166
Award Description: PROVIDE BLAST ANALYSIS REVIEW OF OPERABLE WINDOWS FOR HCHB. REVIEW GGJV SUBMITTALS AND SHOP DRAWINGS FOR CONSISTENCY WITH DESIGN REQUIREMENTS AND ABILITY TO MEET OVERALL BLAST MITIGATION REQUIREMENTS DEFINED FOR THE PROJECT. |
Amount:
$0
Award Description: CHANGE/CORRECTION TO THE ACCOUNTING STRING |
Amount:
$200,000
Award Description: ADDITIONAL ARCHITECTURAL AND ENGINEERING SERVICES |
Amount:
$192,811
Award Description: ARRA MODFICATION TO PROVIDE ARCHITECTURAL AND ENGINEERING SERVICES FOR THE PREPARATION OF MATERIALS ILLUSTRATING A STRATEGY FOR PERIMETER SECURITY DESIGN AT THE HCHB |
Amount:
$3,310
Award Description: COVERAGE FOR EPA BONA FIDE NEED UNTIL OIG AUDIT CAN BE COMPLETED |
Amount:
-$2,266,659
Award Description: DE OBLIGATE UDO. GGA BECAME INSOLVENT AND WAS T4D BY CONTRACTS MAY 18, 2011. PO87 CANCELLED GSA CONTRACT GS-11P-03-MKC-0004 IN ITS ENTIRITY MAY 18,2011. |