contract- RECIPIENT AWARD SUMMARY

W CONSTRUCTION LLC

Clarification of Codes


AWARD OVERVIEW

AWARD OVERVIEW
Agency Name: Department of Agriculture Project Location: CARBON
Award Number: AG82B1C090001 Project Location - State: MT
Funding Amount: $58,524 Project Location - Zip Code: 590680001
Ending Date: 2010-08-01 Congressional District: 00

RECIPIENT INFORMATION (AWARD)

RECIPIENT INFORMATION (AWARD)
Recipient Name: W CONSTRUCTION LLC
Recipient Address: 214 S WILLSON AVE STE B
Recipient City: BOZEMAN
Recipient State: MT
Recipient Zip Code: 597156229
Congressional District: MT-00

DESCRIPTION OF WORK/SERVICE PERFORMED

TAS::12 1102::TAS FOR CAPITAL IMPROVEMENT & MAINTENANCE RECOVERY--FY09 CASCADE BAER WEST FORK ROCK CREEK ROAD #2071 MODIFICATION TWO: THE PURPOSE OF THIS MODIFICATION IS AS FOLLOWS: CONTRACTOR SHALL COMPLETE ALL ITEMS PER EXISTING SPECIFICATIONS AND CONTRACT WITH THE EXCEPTION OF BID ITEM #02240 AGGREGATE SURFACING, BY 09/18/2009. AGGREGATE SURFACING SHALL BE COMPLETED PRIOR TO 07/31/2010. THE CONTRACTOR SHALL BE RESPONSIBLE FOR GRADING AND SHAPING THE ROAD PRIOR TO PLACEMENT OF THE AGGREGATE SURFACING. ANY DAMAGE TO THE ROAD PRISM FROM THE PUBLIC, WEATHER, OR OTHER CAUSES SHALL BE REPAIRED BY THE CONTRACTOR AT NO EXPENSE TO THE GOVERNMENT. THE CONTRACTOR MAY PROCEED WITH PHASE 4 PRIOR TO COMPLETING AGGREGATE SURFACING ON PHASE 3. SEE PAGE 3 FOR THE SUPPLEMENTAL AGREEMENT INFORMATION. NET INCREASE TO THIS CONTRACT IS $58,524.60. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED.






TRANSACTIONS

TRANSACTIONS

Other Awards

Other Awards
Amount: $2,689,739
Award Description: TAS::12 1102::TAS FOR CAPITAL IMPROVEMENT & MAINTENANCE RECOVERY--FY09 CASCADE BAER WEST FORK ROCK CREEK ROAD #2071 ARRA::YES::ARRA
Amount: $58,524
Award Description: TAS::12 1102::TAS FOR CAPITAL IMPROVEMENT & MAINTENANCE RECOVERY--FY09 CASCADE BAER WEST FORK ROCK CREEK ROAD #2071 MODIFICATION TWO: THE PURPOSE OF THIS MODIFICATION IS AS FOLLOWS: CONTRACTOR SHALL COMPLETE ALL ITEMS PER EXISTING SPECIFICATIONS AND CONTRACT WITH THE EXCEPTION OF BID ITEM #02240 AGGREGATE SURFACING, BY 09/18/2009. AGGREGATE SURFACING SHALL BE COMPLETED PRIOR TO 07/31/2010. THE CONTRACTOR SHALL BE RESPONSIBLE FOR GRADING AND SHAPING THE ROAD PRIOR TO PLACEMENT OF THE AGGREGATE SURFACING. ANY DAMAGE TO THE ROAD PRISM FROM THE PUBLIC, WEATHER, OR OTHER CAUSES SHALL BE REPAIRED BY THE CONTRACTOR AT NO EXPENSE TO THE GOVERNMENT. THE CONTRACTOR MAY PROCEED WITH PHASE 4 PRIOR TO COMPLETING AGGREGATE SURFACING ON PHASE 3. SEE PAGE 3 FOR THE SUPPLEMENTAL AGREEMENT INFORMATION. NET INCREASE TO THIS CONTRACT IS $58,524.60. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED.
Amount: $40,600
Award Description: TAS::12 1102::TAS FOR CAPITAL IMPROVEMENT & MAINTENANCE RECOVERY--FY09 CASCADE BAER WEST FORK ROCK CREEK ROAD #2071 MODIFICATION 1 IS ISSUED TO INCREASE THE QUANTITY OF BOULDERS FROM 30 TO 120. ALL BOULDERS CRUSHED WILL BE AT THE EXISTING CONTRACT PRICE, INCLUDING ALL FUTURE BOULDERS ENCOUNTERED ON THIS PROJECT THAT WILL REQUIRE CRUSHING. THIS IS A NET INCREASE IN THE PRICE OF $40,600.29. IF FUTURE ROCKS ARE ENCOUNTERED AND THE FOREST SERVICE WANTS THEM CRUSHED A MODIFICATION WILL BE REQUIRE PRIOR TO WORK BEING DONE. ONE WEEK ADDITIONAL TIME IS ADDED TO PHASE 3. IN ADDITION, CONTRACTING OFFICER IS CHANGED FROM PHIL RAMERIZ TO LINDA M SPITZLER. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED.
Amount: $7,466
Award Description: TAS::12 1102::TAS FOR CAPITAL IMPROVEMENT & MAINTENANCE RECOVERY--FY09 CASCADE BAER WEST FORK ROCK CREEK ROAD #2071 MODIFICATION THREE (3): THE PURPOSE OF THIS MODIFICATION IS AS FOLLOWS: ADD AN ADDITIONAL 16 ROCKS ENCOUNTERED ON PHASE III. NET INCREASE FOR MOD 3 IS $7,466.72. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED.
Amount: $123,901
Award Description: TAS::12 1102::TAS FOR CAPITAL IMPROVEMENT & MAINTENANCE--FY09 CASCADE BAER WEST FORK ROCK CREEK ROAD #2071--RECOVERY - MOD 4 WEST FORK TRAILHEADS--MODIFICATION THREE (3): THE PURPOSE OF THIS MODIFICATION IS AS FOLLOWS: ADD AN ADDITIONAL 16 ROCKS ENCOUNTERED ON PHASE III. NET INCREASE FOR MOD 3 IS $7,466.72.--ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED.
Amount: $52,379
Award Description: TAS::12 1102::TAS FOR CAPITAL IMPROVEMENT & MAINTENANCE RECOVERY - FY09 CASCADE BAER WEST FORK ROCK CREEK ROAD#2071 MOD 08 INCLUDES VARIOUS ITEMS. SEE SUPPLEMENTAL SHEET TO THE MOD. ALL ELSE REMAINS THE SAME. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED.
Amount: $45,133
Award Description: TAS::12 1102::TAS FY09 CASCADE BAER WEST FORK ROCK CREEK ROAD #2071--CAPITAL IMPROVEMENT & MAINTENANCE RECOVERY MOD 06 WAS CREATED AND CANCELLED. MOD 7 IS TO CORRECT LINE ITEMS TO COINCIDE WITH REQUISITION. MOD 8 INCLUDES VARIOUS ITEMS. SEE SUPPLEMENTAL MOD SHEET. MOD 9 IS A SUPPLEMENTAL AGREEMENT TO ADD WORK IN THE SAME VICINITY IN ORDER TO SAVE MOBILIZATION COSTS AND TO NOT HAVE TO BRING IN ANOTHER CONTRACTOR TO WORK AT THE SAME TIME AS THE CURRENT CONTRACTOR IS. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED.
Amount: -$24,974
Award Description: TAS::12 1102::TAS FOR CAPITAL IMPROVEMENT & MAINTENANCE RECOVERY - FY09 CASCADE BAER WEST FORK ROCK CREEK ROAD #2071
Amount: $35,125
Award Description: TAS::12 1102::TAS FOR CAPITAL IMPROVEMENT & MAINTENANCE RECOVERY - FY09 CASCADE BAER WEST FORK ROCK CREEK ROAD #2071
Amount: $0
Award Description: TAS::12 1102::TAS FOR CAPITAL IMPROVEMENT & MAINTENANCE RECOVERY - FY09 CASCADE BAER WEST FORK ROCK CREEK ROAD #2071 MOD 10 - DESIGN QUANTITIES CHANGE. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED.
Amount: $53,665
Award Description: TAS::12 1102::TAS FOR CAPITAL IMPROVEMENT & MAINTENANCE RECOVERY---FY09 CASCADE BAER WEST FORK ROCK CREEK ROAD #2071 MODIFICATION 5. THE PURPOSE OF THIS MODIFICATION IS TO ADD WORK TO STABILIZE SUBGRADE, INSTALL RIPRAP FOR SLOPE STABILIZATION AND REMOVE EXISTING NEW 30" CULVERT AT WILD BILL ENTRANCE, STOCKPILE IN ROCK CREEK BONEYARD. FURNISH AND PLACE 2'X4'X40' CONCRETE CULVERT BURIED 6" BELOW STREAM FLOW LINE. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED.
Amount: $99,686
Award Description: TAS::12 1102::TAS FOR CAPITAL IMPROVEMENT & MAINTENANCE RECOVERY - FY09 CASCADE BAER WEST FORK ROCK CREEK ROAD #2071 MOD 10 - DESIGN QUANTITIES CHANGE. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED.
Amount: $0
Award Description: TAS::12 1102::TAS FOR CAPITAL IMPROVEMENT & MAINTENANCE RECOVERY FY09 CASCADE BAER WEST FORK ROCK CREEK ROAD #2071 MODIFICATION 7 IS TO DELETE THE LUMP SUM ADDED IN MOD 05, THEN CORRECTED ON MOD 06 TO SHOW ITEMS IN LIEU OF LUMP SUM. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED.
Amount: -$26,521
Award Description: TAS::12 1102::TAS FOR CAPITAL IMPROVEMENT & MAINTENANCE RECOVERY - FY09 CASCADE BAER WEST FORK ROCK CREEK ROAD #2071

Project Location Detail

Location Information
Latitude, Longitude 0º 0' 0", 0º 0' 0"
Congressional District 00
City CARBON
County CARBON
State MT
Zip 59068