| Other Awards |
Amount:
$11,935,249
Award Description: TAS::96 3135TAS RECOVERYPROJECT#::140568::RP# REHAB TAINTER GATES AT FT GIBSON AND JOHN REDMOND ARRA |
Amount:
$2,782,747
Award Description: TAS::96 3135::TAS RECOVERYPROJECT#::5790::RP
REHABILITATE AND PAINT TAINTER GATES, FALL RIVER DAM, KANSAS |
Amount:
$281,740
Award Description: RECOVERY - OUTLET WORKS METALWORK RECOATING, NEBRASKA, BUREAU TRACKING NUMBER 61.000, TAS::14 0681::TAS
WORK TO BE PERFORMED INCLUDES THE FOLLOWING: OUTLET WORKS PIPE INTERIOR SURFACE PREPARATION, PIPE SPOT WELDING, FABRICATION AND INSTALLATION OF A NEW 20" ACCESS MANHOLE, OUTLET WORKS PIPE INTERIOR COATING, AND REMOVAL AND DISPOSAL OF COATINGS CONTAINING HEAVY METALS.
|
Amount:
$0
Award Description: RECOVERY - OUTLET WORKS METALWORK RECOATING, NEBRASKA, BUREAU TRACKING NUMBER 61.000, TAS::14 0681::TAS
THIS ADMINISTRATIVE MODIFICATION DELETES FAR 52.204-11 AND INCORPROATES FAR 52.204-11 (DOI DEVIATION) |
Amount:
$1,316
Award Description: VARIATION IN ESTIMATED QUANTITY MODIFICATION . TAS::14 0681::TAS, PROJECT 61.000 |
Amount:
$182,664
Award Description: TAS::96 3135::TAS ARRA::YES::ARRA RECOVERYPROJECT#::140568::RP#
FT. GIBSON & JOHN REDMOND T-GATE REHAB
MODIFICATION FOR REVISIONS TO GATES 10, 11 & 12. |
Amount:
$14,123
Award Description: TAS::96 3135::TAS ARRA::YES::ARRA RECOVERYPROJECT#::140568::RP#
FT. GIBSON & JOHN REDMOND T-GATE REHAB
MODIFICATION AT JOHN REDMOND TO PLACE TAINTER GATE BULKHEAD BACK INTO GATE SLOT #1. |
Amount:
$11,062
Award Description: TAS::96 3135::TAS ARRA::YES::ARRA RECOVERYPROJECT#::140568::RP#
FT. GIBSON & JOHN REDMOND T-GATE REHAB
MODIFICATION TO PROVIDE EQUIPMENT AND SERVICES TO RETRIEVE BULKHEAD FROM GATE ONE AND TRANSPORT |
Amount:
$0
Award Description: TAS::96 3135::TAS ARRA::YES::ARRA RECOVERYPROJECT#::140568::RP#
FT. GIBSON & JOHN REDMOND T-GATE REHAB
MODIFICATION TO CORRECT THE DUNS NUMBER FOR ARRA-REPORTING. |
Amount:
$37,950
Award Description: TAS::96 3135::TAS ARRA::YES::ARRA RECOVERYPROJECT#::140568::RP#
FT. GIBSON & JOHN REDMOND T-GATE REHAB
MODIFICATION TO RETRIEVE THE BULKHEAD WHICH BECAME DETACHED DURING A SIGNIFICANT RAIN EVENT. |
Amount:
$0
Award Description: TAS::96 3135::TAS ARRA::YES::ARRA RECOVERYPROJECT#::140568::RP#
FT. GIBSON & JOHN REDMOND T-GATE REHAB
MODIFICATION FOR WEATHER TIME EXTENSION. |
Amount:
$60,323
Award Description: TAS::96 3135::TAS ARRA::YES::ARRA RECOVERYPROJECT#::141742::RP#
FT. GIBSON & JOHN REDMOND T-GATE REHAB
MODIFICATION ADD 95% UT TESTING TG CHAIN LINKS FOR TAINTER GATES NOT COVERED IN THE ORIGINAL CONTRACT.
|
Amount:
$0
Award Description: FT. GIBSON&JOHN REDMOND T-GATE REHAB
MODIFICATION TO ARC GOUGE THE WELD ON THE SKIN PLATE AND W14X34 ALONG THE BOTTOM OF THE TAINTER GATE THE ENTIRE 40' GATE LENGTH. |
Amount:
$30,796
Award Description: TAS::96 3135::TAS ARRA::YES::ARRA RECOVERYPROJECT#::140568::RP#
FT. GIBSON & JOHN REDMOND T-GATE REHAB
MODIFICATION TO REPAIR BULKHEAD AND CONCRETE PEIR DAMAGE DUE TO A HIGH WATER EVENT. |
Amount:
$35,084
Award Description: TAS::96 3135::TAS ARRA::YES::ARRA RECOVERYPROJECT#::141742::RP#
FT. GIBSON & JOHN REDMOND T-GATE REHAB
MODIFICATION TO ADD ADDITIONAL WORK (HOIST MACHINERY BOLT REPLACEMENT AND HOIST PLATFORM).
|
Amount:
$398,774
Award Description: TAS::96 3135::TAS ARRA::YES::ARRA RECOVERYPROJECT#::140568::RP#
FT. GIBSON & JOHN REDMOND T-GATE REHAB
MODIFICATION TO REHAB AND PAITING GATES 10 & 12 |
Amount:
$0
Award Description: TAS::96 3135::TAS ARRA::YES::ARRA RECOVERYPROJECT#::140568::RP#
FT. GIBSON & JOHN REDMOND T-GATE REHAB
MODIFICATION TO CORRECT FUNDING FOR INTERNAL CONTROLS (ARRA). |
Amount:
$207,000
Award Description: TAS::96 3135::TAS ARRA::YES::ARRA RECOVERYPROJECT#::141742::RP#
FT. GIBSON & JOHN REDMOND T-GATE REHAB
MODIFICATION FOR ADDITIONAL WELD REPAIR QUANTITIES REQUIRED TO REPAIR 30 TAINTER GATES WITH WELD MATERIAL.
|
Amount:
$2,417
Award Description: TAS::96 3135::TAS ARRA::YES::ARRA RECOVERYPROJECT#::5790::RP
REHABILITATE AND PAINT TAINTER GATES, FALL RIVER DAM, KANSAS. MOD IS TO REPAIR CRACKED WELD ON GATE #6 TRUNION ARM. |
Amount:
$14,300
Award Description: TAS::96 3135::TAS ARRA::YES::ARRA RECOVERYPROJECT#::5790::RP
REHABILITATE AND PAINT TAINTER GATES, FALL RIVER DAM, KANSAS. MOD IS TO ADD ADDITIONAL SLIDE SEAL SPACER BAR. |
Amount:
$23,988
Award Description: TAS::96 3135::TAS ARRA::YES::ARRA RECOVERYPROJECT#::5790::RP
REHABILITATE AND PAINT TAINTER GATES, FALL RIVER DAM, KANSAS. MOD IS TO REPAIR CRACKED WELD ON TAINTER GATE #2. |
Amount:
$0
Award Description: TAS::96 3135::TAS ARRA::YES::ARRA RECOVERYPROJECT#::141742::RP#
FT. GIBSON&JOHN REDMOND T-GATE REHAB
MODIFICATION TO EXTEND COMPLETION DATE (JOHN REDMOND ONLY). |
Amount:
$1,144
Award Description: TAS::96 3135::TAS ARRA::YES::ARRA RECOVERYPROJECT#::140568::RP#
FT GIBSON&JOHN REDMOND T-GATE REHAB
JR REPAIRS TO TAINTER GATE 6 |
Amount:
$8,768
Award Description: TAS::96 3135::TAS ARRA::YES::ARRA RECOVERYPROJECT#::141742::RP#
FT GIBSON&JOHN REDMOND T-GATE REHAB, FORT GIBSON, OK AND JOHN REDMOND, KS.
MODIFICATION TOREMOVE AND REPLACE 3 FEET OF WEB AT THE BOTTOM EAST CORNER OF THE GATE.(FT GIBSON). |
Amount:
$17,770
Award Description: TAS::96 3135::TAS ARRA::YES::ARRA RECOVERYPROJECT#::141742::RP#
FT GIBSON AND JOHN REDMOND T-GATE REHAB.
FG G9 REPLACE BRACE ON W TRUNNION |
Amount:
$96,930
Award Description: TAS::96 3135::TAS ARRA::YES::ARRA RECOVERYPROJECT#::141742::RP#
FT GIBSON&JOHN REDMOND T-GATE REHAB
BRACE REPAIRS TO GATES 13 TO 30 |
Amount:
$64,750
Award Description: TAS::96 3135::TAS ARRA::YES::ARRA RECOVERYPROJECT#::141742::RP#
FT GIBSON&JOHN REDMOND T-GATE REHAB
00020 FG-ARCH GOUG SEAM WELD BTM GATES 25-30 |
Amount:
$51,386
Award Description: TAS::96 3135::TAS ARRA::YES::ARRA RECOVERYPROJECT#::141742::RP#
FT GIBSON AND JOHN REDMOND T-GATE REHAB
FG GATE WEB REPAIRS ON BOTTOM GRIDER MOD#21 |
Amount:
$2,288
Award Description: TAS::96 3135::TAS ARRA::YES::ARRA RECOVERYPROJECT#::141742::RP#
FT GIBSON&JOHN REDMOND T-GATE REHAB
00018 FG GATE 11 WEB REPAIR ON BOTTOM GIRDER |
Amount:
$4,835
Award Description: TAS::96 3135::TAS ARRA::YES::ARRA RECOVERYPROJECT#::140559::RP#
FALL RIVER PAINT TAINTER GATES, FALL RIVER LAKE, KANSAS.
MODIFICATION TO REPAIR 2 CRACKED WELDS ON GT8 TRUN ARM. |
Amount:
$0
Award Description: TAS::96 3135::TAS ARRA::YES::ARRA RECOVERYPROJECT#::140559::RP#
FALL RIVER PAINT TAINTER GATES
MODIFICATION TO EXTEND CONTRACT COMPLETION DATE DUE TO WEATHER. |
Amount:
-$39,989
Award Description: FT GIBSON TAINTER GATES-ARRA |
Amount:
$65,317
Award Description: FT GIBSON TAINTER GATES-ARRA |