| Other Awards |
Amount:
$18,274,884
Award Description: RECOVERY STLI PMIS# 152319
STATUE OF LIBERTY NATIONAL MONUMENT, STABILIZE ELLIS ISLAND SEAWALL
THE WORK DESCRIBED AS FOLLOWS: 1. INSTALLATION OF STEEL SHEET PILING AND TREMIE CONCRETE; 2. INSTALLATION OF STEEL H-PILES INCLUDING PRE-DRILLING THROUGH TIMBER CRIBBING; 3. INSTALLATION OF PRESSURE GROUTED POST-TENSIONED SOIL ANCHORS AND ASSOCIATED ASSEMBLAGES; 4. INSTALLATION OF CAST-IN-PLACE CONCRETE BEAMS INCLUDING TIE-IN TO EXISTING STRUCTURES; 5.EXCAVATION AND BACKFILL INCLUDING INSTALLATION OF GEOTEXTILE FABRIC; 6. REPAIR OF GRANITE MASONRY BLOCK FACING INCLUDING UNDERWATER RECOVERY, RESETTING, AND REPOINTING AND INCIDENTAL WORK. |
Amount:
$10,504
Award Description: RECOVERY STLI PMIS# 152319
STATUE OF LIBERTY NATIONAL MONUMENT, STABILIZE ELLIS ISLAND SEAWALL, THIS MODIFICATION 0001 ADDS FUNDING TO EXTEND A HAUL ROAD AND TEMPORARILY FILL SINKHOLES REQUIRED TO SAFELY PURSUE WORK. |
Amount:
$499,286
Award Description: STLI-152319, THE WITHIN SCOPE WORK OF MODIFICATION 0007 IS TO ADD FUNDS AND SETTLE ISSUES ASSOCIATED WITH INCREASES IN ESTIMATED QUANTITIES AND DIFFERING SITE CONDITIONS. THIS MOD IS FUNDED WITH NON-ARRA FUNDING. |
Amount:
$77,117
Award Description: RECOVERY STLI PMIS# 152319
STATUE OF LIBERTY NATIONAL MONUMENT, STABILIZE ELLIS ISLAND SEAWALL, THIS WITHIN SCOPE MODIFICATION 0004 SETTLES COSTS RELATED TO A DIFFERING SITE CONDITION AND ADDS FIRM-FIXED-UNIT PRICED ITEMS TO ADDRESS THE POSSIBILITY OF ADDITIONAL DIFFERING SITE CONDITIONS. |
Amount:
$336,647
Award Description: RECOVERY STLI PMIS# 152319
STATUE OF LIBERTY NATIONAL MONUMENT, STABILIZE ELLIS ISLAND SEAWALL, THIS MODIFICATION 0002 ADDS FUNDING TO EXTEND WORK ZONE 1 FOR PROTECTION OF PARK CULTURAL RESOURCES AND REQUIRE ADDITIONAL CORE DRILLING AND REMOVAL OF CONCRETE MASS (DIFFERING SITE CONDITION). THIS MOD IS WITHIN THE SCOPE OF THE CONTRACT. |
Amount:
$75,926
Award Description: RECOVERY STLI PMIS# 152319
STATUE OF LIBERTY NATIONAL MONUMENT, STABILIZE ELLIS ISLAND SEAWALL, THIS WITHIN SCOPE MODIFICATION 0005 SETTLES COSTS RELATED TO A DIFFERING SITE CONDITION AND ADDS QUANTITIES TO ADDRESS OVERRUNS OF BELOW WATER SEAWALL REPAIR. |
Amount:
$0
Award Description: RECOVERY STLI PMIS# 152319
STATUE OF LIBERTY NATIONAL MONUMENT, STABILIZE ELLIS ISLAND SEAWALL, THIS MODIFICATION 0003 ADDS NEW CONTRACT CLAUSE 52.209-09 (ALT I) UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY MATTERS (JAN 2011)AS REQUIRED. |
Amount:
$613,209
Award Description: RECOVERY STLI PMIS# 152319
STATUE OF LIBERTY NATIONAL MONUMENT, STABILIZE ELLIS ISLAND SEAWALL, THIS WITHIN SCOPE MODIFICATION 0006 ADDS WORK ASSOCIATED WITH ADDITIONAL REPAIR NEEDED FOR CORNER-1 AND ADDS QUANTITIES TO ADDRESS OVERRUNS OF ESTIMATED QUANTITIES FOR TREMIE CONCRETE AND BELOW WATER SEAWALL REPAIR. |
Amount:
$0
Award Description: STLI 152319 ARRA STABLIZE ELLIS ISLAND, STATUE OF LIBERTY NATIONAL PARK, CHANGES TO WORK SCOPE DUE TO DIFFERING SITE CONDITIONS |
Amount:
$0
Award Description: STLI 1522319 ARRA
STATUE OF LIBERTY NATIONAL MONUMENT, STABILIZE ELLIS ISLAND SEAWALL
ALLOWANCE OF WORK IN WZ1/1A TO CONTINUE BEYOND JUNE 1, 2012. |
Amount:
$0
Award Description: RECOVERY
STLI 152319 STABLIZE ELLIS ISLAND SEAWALL
MOD 17 INCORPORATES A SETTLEMENT AGREEMENT FOR NONCOMPLIANCE WITH CONTRACT REQUIREMENTS, AND CHANGES DUE TO DIFFERING SITE CONDITIONS. |
Amount:
$0
Award Description: RECOVERY
STLI-152319, MODIFICATION 0009 IS ISSUED UNILATERALLY TO ADD FUNDS ASSOCIATED WITH INCREASES IN ESTIMATED QUANTITIES AND DIFFERING SITE CONDITIONS. A BILATERAL MODIFICATION WILL BE ISSUED UPON COMPLETION OF NEGOTIATIONS FOR THE WORK ASSOCIATED WITH THE DIFFERING SITE CONDITIONS. |
Amount:
$0
Award Description: THE PURPOSE OF THIS MODIFICATION IS TO MAKE ADMINISTRATIVE CHANGES TO THE CONTRACT WITHIN THE CONTRACT LINE ITEM (CLIN) STRUCTURE IN ORDER TO FACILITATE THE GOVERNMENT+S CONVERSION TO UPDATED SOFTWARE (FBMS). THIS MODIFICATION MADE CHANGES TO THE DELIVERY, START, AND/OR END DATES, CHANGING EACH CLIN TO BE CONSISTENT WITH THE CURRENT CONTRACT DATES. THIS MODIFICATION DOES NOT CHANGE ANY REQUIREMENTS, FUNDING, DELIVERY, OR PERFORMANCE DATES OF THE CONTRACT. ALL TERMS AND CONDITIONS REMAIN UNCHANGED. |
Amount:
$0
Award Description: ARRA STLI 152319 STABLIZE ELLIS ISLAND SEAWALL
MOD 18 INCORPORATES A SETTLEMENT AGREEMENT FOR DELETED WORK, AN EXTENSION TO THE PERIOD OF PERFORMANCE, AND CHANGES DUE TO DIFFERING SITE CONDITIONS. |
Amount:
$0
Award Description: RECOVERY
STLI-152319, MODIFICATION 0015 IS ISSUED UNILATERALLY TO MAKE REPAIRS TO CONCRETE AT THE FLAGPOLE. A BILATERAL MODIFICATION WILL BE ISSUED UPON COMPLETION OF NEGOTIATIONS FOR THE WORK. |
Amount:
$0
Award Description: RECOVERY STLI PMIS# 152319
STATUE OF LIBERTY NATIONAL MONUMENT, STABILIZE ELLIS ISLAND SEAWALL, THIS MODIFICATION 0012 SETTLES COSTS FOR IN-SCOPE WORK IN WORK ZONE 5 DUE TO DIFFERING SITE CONDITIONS AND DEFINITIZES UNILATERAL MODIFICATIONS 0009 AND 0010. |
Amount:
$0
Award Description: RECOVERY
STLI-152319, MODIFICATION 0010 IS ISSUED TO MAKE A CORRECTION TO THE PREVIOUSLY ISSUED UNILATERAL MODIFICAITON 0009.
A BILATERAL MODIFICATION WILL BE ISSUED UPON COMPLETION OF NEGOTIATIONS FOR THE WORK ASSOCIATED WITH MODIFICATION 0009 DIFFERING SITE CONDITIONS. |
Amount:
$0
Award Description: RECOVERY
STLI-152319, MODIFICATION 0014 IS ISSUED UNILATERALLY TO MAKE REPAIRS TO A VOID AT THE WALL OF HONOR. A BILATERAL MODIFICATION WILL BE ISSUED UPON COMPLETION OF NEGOTIATIONS FOR THE WORK ASSOCIATED WITH THESE DIFFERING SITE CONDITIONS. |
Amount:
$0
Award Description: RECOVERY
STLI 152319 STABILIZE ELLIS ISLAND SEAWALL, HUDSON COUNTY NJ
DELETION OF UNDERWATER REPAIRS |
Amount:
$25,000
Award Description: STLI-152319, THE WITHIN SCOPE WORK OF MODIFICATION 0008 IS TO ADD FUNDS AND SETTLE ISSUES ASSOCIATED WITH INCREASES IN ESTIMATED QUANTITIES AND DIFFERING SITE CONDITIONS. THIS MOD IS FUNDED WITH NON-ARRA FUNDING. |
Amount:
$0
Award Description: OTHER FUNCTIONS
ARRA STLI 152319
THIS MODIFICATION NO 21 IS ISSUED TO INCORPORATE ADDITIONAL WORK WITHIN SCOPE AT CORNER 3 AND ON THE PEDESTRIAN BRIDGE. |
Amount:
$0
Award Description: STLI 152319 ARRA STABLIZE ELLIS ISLAND, STATUE OF LIBERTY NATIONAL PARK, DEFINITIZE NEGOTIATED SETTLEMENT OF GOVERNMENT'S ACCEPTANCE OF NONCOMPLIANT WORK IN CONSIDERATION OF VEGETATION MANAGEMENT WORK TO BE COMPLETED ON THE CONSTRUCTION SITE, AND EXTEND THE PERIOD OF PERFORMANCE THROUGH SEPT. 29, 2012. |