| Other Awards |
Amount:
$0
Award Description: TAS::17 1116::TAS RECOVERYPROJECT#::PE1069M::RP# REPAIR GAS PIPE AREA 62 (BS22), MCB, CAMP PENDLETON, CA ARRA::YES::ARRA |
Amount:
$1,688,732
Award Description: TAS::17 1116::TAS RECOVERYPROJECT#::PE1069M::RP# REPAIR GAS PIPE AREA 62 (BS22), MCB, CAMP PENDLETON, CA
ARRA::YES::ARRA |
Amount:
$172,329
Award Description: TAS::21 2022::TAS REPLACE ROOFS BUILDINGS 2746 AND 2747 AT THE NAVAL SUPPORT ACTIVITY, CRANE, INDIANA ARRA::YES::ARRA |
Amount:
$98,069
Award Description: TAS::21 2066::TAS ARRA TTB ROOFS CRJMTC ARRA::YES::ARRA |
Amount:
$7,212,197
Award Description: TAS::57 3404::TAS RECOVERYPROJECT#::FJXT101012::RP# REPAIR DORM 445; DOVER AFB, DE. DESIGN/BUILD DORMITORY REPAIR |
Amount:
$102,203
Award Description: TAS::57 3404::TAS RECOVERYPROJECT#::RNGF091020::RP# REPLACE POL SYSTEM; NEW BOSTON AFS, NH ARRA::YES::ARRA |
Amount:
$121,706
Award Description: TAS::57 3404::TAS RECOVERY - MXDP091030 - ENERGY-INSTALL CAPACITOR SYSTEM FOR POWER FACTOR CONVERSION ARRA::YES::ARRA |
Amount:
$62,353
Award Description: TAS::57 3404::TAS RECOVERYPROJECT#::FJXT101012::RP# REPAIR DORM 445; DOVER AFB, DE. DESIGN/BUILD DORMITORY REPAIR |
Amount:
$2,515,961
Award Description: TAS::57 3404::TAS RECOVERY - FJXT091013 - REPAIR WATER STORAGE (S/R)ARRA::YES::ARRA |
Amount:
$5,490,590
Award Description: TAS::57 3404::TAS, RECOVERY, FA3002-08-D-0012 6X01, PROJECT #'S, KWRD 07-0063A CONSTRUCT PAVEMENTS NORTH RAMP, KWRD 07-0063B CONSTRUCT PAYMENTS NORTHRAMP REPAIR, KWRD 08-0067 REPAIR CONCRETE SLABS TAXIWAY F, - 0063A: THE WORK TO BE PERFORMED ENTAILS REMOVING 2600 SQUARE YARDS OF ASPHALT SURFACE ON THE NORTH RAMP AND REPLACED WITH AIRCRAFT RATED PCC PAVEMENT. ARRA::YES::ARRA |
Amount:
$1,631,128
Award Description: TAS::57 3744::TAS -- RECOVERY - PDPG070112-BLAST FENCES TANGO ROW (ALTERNATE)
TAS::57 3744::TAS -- RECOVERY - INSTALL CABLE RETENTION PERIMETER FENCE ARRA::YES::ARRA |
Amount:
$0
Award Description: TAS::57 3744::TAS -- RECOVERY - PDPG070112 - BLAST FENCES TANGO ROW (ALTERNATE)
TAS::57 3744::TAS -- RECOVERY - PDPG080160 - INSTALL CABLE RETENTION PERIMETER FENCE |
Amount:
$0
Award Description: RECOVERYPROJECT#::PE1069M::RP# REPAIR GAS PIPE AREA 62 (BS22), MCB, CAMP PENDLETON, CA. THE PURPOSE OF THE MODIFICATION IS TO INCORPORATE ADDITIONAL FAR CLAUSES. |
Amount:
-$174,961
Award Description: RECOVERYPROJECT#::PE1069M::RP# REPAIR GAS PIPE AREA 62, MCB, CAMP PENDLETON, CA. THIS MODIFICATION INCORPORATES THE FINAL DESIGN ALONG WITH THE ADDS AND DELETES. |
Amount:
-$107,813
Award Description: TAS::57 3404::TAS RECOVERY - MXDP091030 - ENERGY-INSTALL CAPACITOR SYSTEM FOR POWER FACTOR CONVERSION ARRA::YES::ARRA |
Amount:
$114,732
Award Description: TAS::57 3404::TAS RECOVERPROJECT#::FJXT051018::RP# REDESIGN INCLUDING GATE AND CHECK VALVES; AND, CHLORINE INJECTION PIPING.
TAS::57 3404::TAS RECOVERPROJECT#::FJXT051013::RP# REDESIGN INCLUDING CROSS CONNECTION AND VALVE CHAMBER BLDG. |
Amount:
$75,620
Award Description: TAS::57 3404::TAS RECOVERPROJECT#::FJXT051018::RP# REDESIGN INCLUDING GATE AND CHECK VALVES; AND, CHLORINE INJECTION PIPING.
TAS::57 3404::TAS RECOVERPROJECT#::FJXT051013::RP# REDESIGN INCLUDING CROSS CONNECTION AND VALVE CHAMBER BLDG. ADD WORK--DIFFERING SITE CONDITIONS AND REQUIRED DESIGN MODIFICATIONS ARRA::YES::ARRA |
Amount:
$0
Award Description: FUNDING SUBCLIN |
Amount:
$0
Award Description: TAS::57 3404::TAS RECOVERYPROJECT#::FJXT101012::RP# REPAIR DORMITORY 445, DOVER AFB, DE HEAVY ENGINEERING REPAIR AND CONSTRUCTION SERVICES TASK ORDER TO REPARI DORMITORY 445 AT DOVER AFB, DELAWARE FOR PROJECT FJXT 10-1012 MODIFICATION TO INCORPORATE THE REVISED STATEMENT OF WORK DATED 01 AUGUST 2011 AND EXTEND THE PERIOD OF PERFORMANCE TO 30 AUGUST 2011. |