Amount:
$2,697,573
Award Description: TAS::96 3135::TAS RECOVERY: PERIODIC INSPECTION OF SWD LEVEES |
Amount:
$1,158,387
Award Description: TAS::96 3135::TAS, RECOVERY - GEOTECHNIAL ENGINEERING SERVICES, INSTRUMENTATION WORK AT THE J. PERCY PRIEST PROJECT OF THE NASHVILLE DISTRICT USACE. |
Amount:
$151,722
Award Description: TAS::96 3135::TAS - GEOTECHNICAL INVESTIGATIONS AT WINFIELD LOCKS AND DAM |
Amount:
$64,495
Award Description: TAS::96 3135::TAS - ROCK CORE STRENGTH TESTING, SUTTON DSA, SUTTON DAM, SUTTON, WV |
Amount:
$246,853
Award Description: TAS::96 3135::TAS, RECOVERY - GEOTECHNICAL ENGINEERING SERVICES, WATER LEAK STOPPAGE AT THE BARKLEY POWER PLANT OF THE NASHVILLE DISTRICT USACE. |
Amount:
$484,754
Award Description: TAS::96 3135::TAS - REHABILITATION OF FOUNDATION DRAINS AT SUTTON LAKE, SUTTON, WV ARRA::YES::ARRA |
Amount:
$5,205
Award Description: TAS::96 3135::TAS - REHABILITATION OF FOUNDATION DRAINS AT SUTTON LAKE, SUTTON, WV. ARRA::YES::ARRA |
Amount:
$0
Award Description: TAS::96 3135::TAS MODIFICATION TO DRILLING AT SUTTON DAM, WV ARRA::YES::ARRA |
Amount:
$190,000
Award Description: TAS::96 3135::TAS - LENGTHENING OF FOUNDATION DRAINS AT SUTTON DAM, SUTTON, WV |
Amount:
$193,229
Award Description: TAS::96 3135::TAS - DAM SAFETY ASSURANCE EVALUATION FOR SUTTON LAKE, WV |
Amount:
$118,763
Award Description: TAS::96 3135::TAS - SEEPAGE AND SLOPE STABILITY ANALYSES, WINFIELD LOCKS AND DAM, RED HOUSE, WV |
Amount:
$2,312,688
Award Description: TAS::96 3135::TAS PERIODIC LEVEE INSPECTIONS OF FLOOD CONTROL PROJECTS IN VARIOUS LOCATIONS THROUGHOUT SOUTHERN INDIANA UNDER IDC FOR GEOTECHNICAL SERVICES WITHIN THE GREAT LAKES AND OHIO RIVER MISSION BOUNDARIES |
Amount:
$667,077
Award Description: TAS::96 3135::TAS
ARRA-LEVEE PERIODIC INSPECTION
|
Amount:
$260,681
Award Description: RECOVERYPROJECT#::17840::RP# DRILL FOR FOUNDATION DRAIN LENGTHENING FOR SUTTON LAKE, SUTTON WV. |
Amount:
$0
Award Description: TAS::96 3135::TAS ARRA::YES::ARRA RECOVERYPROJECT#::17840::RP# * REHABILITATE FOUNDATION DRAINS TO REDUCE THE RISK OF DAM FAILURE FOUNDATION DRAIN LENGTHENING AT SUTTON LAKE, SUTTON, WV. |
Amount:
$147,125
Award Description: RECOVERYPROJECT#::17840::RP# - SUTTON DAM UPLIFT CELL REHABILITATION AT SUTTON DAM, SUTTON, WV |
Amount:
$0
Award Description: TAS::96 3135::TAX ARRA::YES::ARRA RECOVERYPROJECT#::324170::RP# 324170 LEVEE PERIODIC INSPECTION, VARIOUS LOCATIONS.
THE CONTRACTOR SHALL PERFORM A LEVEE SAFETY PERIODIC INSPECTION (PI) ON THE LEVEE SYSTEMS INDICATED ON THE SUMMARY SHEETS INCLUDED AS ENCLOSURE 2 OF THIS SCOPE OF WORK. THE LEVEE SYSTEMS TO BE INSPECTED MAY CONSIST OF MULTIPLE SEGMENTS AND HAVE MULTIPLE SPONSORS PER SYSTEM. THE PURPOSE OF PIS IS TO VERIFY PROPER OPERATION AND MAINTENANCE, EVALUATE OPERATIONAL ADEQUACY AND STRUCTURAL STABILITY, REVIEW DESIGN CRITERIA TO IDENTIFY CHANGES IN CURRENT DESIGN STANDARDS, IDENTIFY FEATURES TO MONITOR OVER TIME, AND IMPROVE THE ABILITY TO COMMUNICATE THE OVERALL CONDITION. |
Amount:
$3,549,501
Award Description: TAS::96 3135::TAX ARRA::YES::ARRA RECOVERYPROJECT#::324170::RP# 324170 LEVEE PERIODIC INSPECTION, VARIOUS LOCATIONS.
THE CONTRACTOR SHALL PERFORM A LEVEE SAFETY PERIODIC INSPECTION (PI) ON THE LEVEE SYSTEMS INDICATED ON THE SUMMARY SHEETS INCLUDED AS ENCLOSURE 2 OF THIS SCOPE OF WORK. THE LEVEE SYSTEMS TO BE INSPECTED MAY CONSIST OF MULTIPLE SEGMENTS AND HAVE MULTIPLE SPONSORS PER SYSTEM. THE PURPOSE OF PIS IS TO VERIFY PROPER OPERATION AND MAINTENANCE, EVALUATE OPERATIONAL ADEQUACY AND STRUCTURAL STABILITY, REVIEW DESIGN CRITERIA TO IDENTIFY CHANGES IN CURRENT DESIGN STANDARDS, IDENTIFY FEATURES TO MONITOR OVER TIME, AND IMPROVE THE ABILITY TO COMMUNICATE THE OVERALL CONDITION. |
Amount:
-$37
Award Description: TAS::96 3135::TAS - DRILLING SERVICES FOR WINFIELD L&D, RED HOUSE, WV - MODIFICATION ARRA::YES::ARRA |
Amount:
$0
Award Description: TAS::96 3135::TAS, RECOVERY - GEOTECHNICAL ENGINEERING SERVICES, WATERSTOP LEAKAGE REPAIRS AT THE BARKLEY POWER PLANT OF THE NASHVILLE DISTRICT USACE. |
Amount:
$45,180
Award Description: TAS::96 3135::TAS SUTTON DAM DSA, SUTTON, WV. ARRA::YES::ARRA |
Amount:
$0
Award Description: TAS::96 3135::TAS ARRA::YES::ARRA TIME EXTENSION FOR SUTTON DSA, SUTTON LAKE, WV FROM 30 NOV 2010 - 21 MAR 2011. |
Amount:
$967,423
Award Description: TAS::96 3135::TAS ARRA::YES::ARRA RECOVERYPROJECT#:: 324170 ?::RP# ?PROJECT TITLE: PERIODIC INSPECTION OF LEVEES (324170) O&M INSPECTION OF LEVEE SYSTEM NO. 5, LEVEE SYSTEMS LOCATED IN TWO REGIONS: SOUTHWEST FLORIDA MANAGEMENT DISTRICT AND ST. JOHNS RIVER WATER MANAGEMENT DISTRICT |
Amount:
$319,794
Award Description: TAS::96 3135::TAS RECOVERY PROJECT#::140588::RP# INVESTIGATE SLOUGHING OF OUTLET CHANNEL, SKIATOOK LAKE |
Amount:
-$827
Award Description: ARRA TAS::96 3135::TAS REDUCTION IN DRILLING FOR THE SUTTON LAKE DRAINS REHABILITATION, SUTTON, WV. |
Amount:
-$13,935
Award Description: TAS::96 3135:: TAS RECOVERYPROJECT#::140588::INVESTIGATE SLOUGHING OF OUTLET CHANNEL - PHASE I INSTRUMENTATION INSTALLATION, TESTING, MONITORING AND ANALYSIS. |
Amount:
-$45,676
Award Description: TAS::96 3135::TAS ARRA::YES::ARRA RECOVERYPROJECT#:: 324170 ?::RP# ?PROJECT TITLE: PERIODIC INSPECTION OF LEVEES (324170) O&M INSPECTION OF LEVEE SYSTEM NO. 5, LEVEE SYSTEMS LOCATED IN TWO REGIONS: SOUTHWEST FLORIDA MANAGEMENT DISTRICT AND ST. JOHNS RIVER WATER MANAGEMENT DISTRICT |
Amount:
$0
Award Description: W912BV-08-D-1005 GEOTECHNICAL SERVICES, EXTEND POP |
Amount:
-$30,077
Award Description: PERIODIC INSPECTION OF LEVEES NO. 5 |