contract- RECIPIENT AWARD SUMMARY
MARON CONSTRUCTION CO., INC.
| AWARD OVERVIEW |
|
Agency Name: General Services Administration |
Project Location:
PROVIDENCE |
|
Award Number: GSP0110BZ5037 |
Project Location - State: RI |
|
Funding Amount:
$1,965 |
Project Location - Zip Code: 029031737 |
|
Ending Date:
2011-04-02 |
Congressional District: 02 |
RECIPIENT INFORMATION (AWARD)
| RECIPIENT INFORMATION (AWARD) |
|
Recipient Name:
|
MARON CONSTRUCTION CO., INC. |
|
Recipient Address:
|
180 BUTTONHOLE DR |
|
Recipient City:
|
PROVIDENCE |
|
Recipient State:
|
RI |
|
Recipient Zip Code:
|
029095746 |
|
Congressional District:
|
RI-02 |
DESCRIPTION OF WORK/SERVICE PERFORMED
INSTALL TWELVE ADDITION DIMMABLE BALLASTS
| Other Awards |
Amount:
$9,430,000
Award Description: TAS::21 2081::TAS RECOVERYPROJECT#::74677::RP# FULL FACILITY RESTORATION OF THE GORDON M. CRAIG U.S. ARMY RESERVE CENTER, BROCKTON, MA |
Amount:
$115,393
Award Description: TAS::21 2081::TAS ARRA::YES::ARRA CASE JC016 REMOVE RUSTED STUDS AND MOLDY INSULATION; CASE JC017 INCREASE ELECTRIC WIRE SIZE; CASE JC018 REMOVE OMS SLOPED SLAB; CASE JC019 DELETE WATER SOFTENERS; CASE JC020 REPLACE WIRE MESH WITH REBAR; CASE JC021 EXTENDED OVERHEAD; CASE JC022 ADD FLOOR DRAINS, FULL FACILITY RESTORATION, GORDON M. CRAIG U.S. ARMY RESERVE CENTER, BROCKTON, MA |
Amount:
$28,612
Award Description: TAS::21 2081::TAS ARRA::YES::ARRA CASE 024 RELOCATION OF ELECTRICAL PANELS IN OMS; CASE 030 REDESIGN OF STRUCTURAL SHORING, BRAC FULL FACILITY RESTORATION OF GORDON M. CRAIG U.S. ARMY RESERVE CENTER, BROCKTON, MA |
Amount:
$187,186
Award Description: TAS::21 2081::TAS ARRA::YES::ARRA CASE 029 APPLY MASONRY WATERPROOFING, WEEP HOLES AND CHANGE INSULATION AT TRAINING BUILDING; CASE 033 INSTALL STRUCTURAL STEEL SHORING IN TRAINING BUILDING, FULL FACILITY RESTORATION OF GORDON M. CRAIG U.S. ARMY RESERVE CENTER, BROCKTON, MA |
Amount:
$145,530
Award Description: TAS::21 2081::TAS ARRA::YES::ARRA CASE JC001A REMOVE DEBRIS; CASE JC002 ASBESTOS TESTING; CASE JC003 REMOVAL OF ASBESTOS FLOOR TILE; CASE JC004 REMOVE UNSUITABLE SOIL; CASE JC005 REPLACE DRYWALL; CASE JC006 PERFORM NONDESTRUCTIVE TESTING OF SLABS; CASE JC007 INSTALL PLASTIC LAMINATE SHELVING; CASE JC008 REMOVAL OF ASBESTOS-CONTAINING MATERIAL; CASE JC009 INSTALL 20' OF TYPE A WALL; CASE JC010 RANDOM SAMPLING OF SUSPECTED ASBOSTOS-CONTAINING MASTIC; CASE JC011 INSTALL PVC AND OIL LINE UNDER GROUND TO ELEVATOR PIT; CASE JC012 REMOVE MASTIC AND TILE FROM BATHROOMS; CASE JC013 INSTALL NEW STUDS ON WALL; CASE JC014 INSTALL 2 LARGE ROOF LOUVERS; CASE JC015 REMOVAL AND DISPOSAL OF CONCRETE PADS; FULL FACILITY RESTORATION, GORDON M. CRAIG U.S. ARMY RESERVE CENTER, BROCKTON, MA |
Amount:
$62,933
Award Description: TAS::21 2081::TAS ARRA::YES::ARRA PROVIDE GATE POWER; INSTALL INSULATED GROUNDING CONDUCTOR; PROVIDE ELECTRICAL CIRCUITS; CHANGE COUNTERTOPS; EMERGENCY SHORING WORK; CONVERT STALLS TO HANDICAPPED-ACCESSIBLE; ADD CIRCUIT AND OUTLETS; ADD WATER TANK SUPPORT; REPOINT STAIRWELL, DESIGN/BUILD FULL FACILITY RESTORATION OF GORDON M. CRAIG U.S. ARMY RESERVE CENTER, BROCKTON, MA |
Amount:
$106,693
Award Description: TAS::21 2081::TAS ARRA::YES::ARRA INSTALL NEW ROOF ON EXISTING ORGANIZATIONAL MAINTENANCE SHOP, DESIGN/BUILD FULL FACILITY RESTORATION GORDON M. CRAIG U.S. ARMY RESERVE CENTER, BROCKTON, MA |
Amount:
$0
Award Description: TAS::21 2081::TAS ARRA::YES::ARRA CLIN NUMBERING CORRECTIONS, FULL FACILITY RESTORATION, GORDON M CRAIG U.S. ARMY RESERVE CENTER, BROCKTON, MA |
Amount:
$745,000
Award Description: TAS::21 2081::TAS ARRA::YES::ARRA INCORPORATE REVISED AND ADDITIONAL DRAWINGS TO THE CONTRACT, DESIGN/BUILD FULL FACILITY RESTORATION OF GORDON M. CRAIG U.S. ARMY RESERVE CENTER, BROCKTON, MA |
Amount:
$0
Award Description: TAS::21 2081::TAS ARRA::YES::ARRA CASE JC001 CHANGE SITE SAFETY AND HEALTH OFFICER (SSHO) DUTIES, FULL FACILITY RESTORATION, GORDON M. CRAIG U.S. ARMY RESERVE CENTER, BROCKTON, MA |
Amount:
$0
Award Description: TAS::21 2081::TAS ARRA::YES::ARRA EXERCISE OPTION FOR PAVING AT PERSONALLY-OPERATED VEHICLE AND MILITARY EQUIPMENT PARKING AREAS, FULL FACILITY RESTORATION, GORDON M. CRAIG U.S. ARMY RESERVE CENTER, BROCKTON, MA |
Amount:
$125,979
Award Description: ARRA GIAMI/MCMAHON BUILDING TUNE-UPS |
Amount:
$203,418
Award Description: "RECOVERY" EXERCISE OPTION #6 OF AWARD LINE ITEM TO PROVIDE AND INSTALL LECM-5, TWO-WAY VALVES FOR HW/CW AND VSDS |
Amount:
$301,484
Award Description: ARRA ENERGY EFFICIENCY IMPROVEMENTS AT THE PROVIDENCE FEDERAL COURTHOUSE AND PASTORE FEDERAL BUILDING/USPO |
Amount:
$0
Award Description: DONOHUE ENERGY UPGRADES |
Amount:
$409,900
Award Description: TAS::47 4543::TAS ENERGY CONSERVATION MEASURES TO INCLUDE A NEW CHILLER, RE-CAULK, PAINT AND PRIME WINDOWS, AND REPLACE 2 VARIABLE FREQUENCY DRIVES AT THE DONOHUE FB WORCESTER MA |
Amount:
$10,711
Award Description: MODIFICATION TO CHANGE WIRELESS SENSORS TO WIRED AND PROVIDE AND INSTALL SURFACE MOUNTED LIGHT FIXTURES |
Amount:
$234,141
Award Description: ARRA BUILDING TUNE-UPS AT GIAIMO FEDERAL BUILDING IN NEW HAVEN, CT AND MCMAHON COURTHOUSE IN BRIDGEPORT, CT. |
Amount:
$0
Award Description: ENERGY CONSERVATION MEASURES, DONOHUE FB, WORCESTER, MA |
Amount:
$0
Award Description: CONSERVATION MEASURES AT THE DONOHUE FB, WORCESTER, MA |
Amount:
-$8
Award Description: TAS::21 2081::TAS ARRA::YES::ARRA CASE JC023 INSTALL LIGHT FIXTURE WITH DRYWALL FRAME; CASE JC035 ADD TYPE J WALL ON TOP OF CMU; CASE JC036 ADDITIONAL WORK FOR DELAYED INSTALLATION OF SILT FENCE; CASE JC043 ADD HOSE BIBS UNDER SINKS IN RESTROOMS; CASE JC049R CREDIT FOR STANDARD EPOXY PAINT INISH IN LIEU OF TOWELED FINISH; CASE JC052 INSULATE ROOF DRAIN PIPING; CASE JC054 KEEP AND REUSE EXTERIOR LIGHTS; CASE JC055 INSTALL 12 PLASTIC FRAMES FOR DIFFUSERS; CASE JC056 PROVIDE 2 SEPARATE CIRCUITS FOR HEATERS; CASE JC057 TIE IN WATERLINE TO AVOID EXISTING SEWER; CASE JC059 PAINT WINDOW SILLS; CASE JC064 CHANGE PAINT COLOR IN OFFICES; CASE JC065R PROVIDE TEMPORARY HEATING FOR CONSTRUCTION DURING COLD WEATHER; CASE JC066 PROVIDE TEMPORARY HEATING IN OMS BUILDING; CASE JC067R INSTALL MANUFACTURED CANOPY SYSTEM; CASE JC068 REPLACE EXISTING WATER SUPPLY LINE; CASE JC069RR PREFINISH ALL WOOD DOORS; CASE JC071 WATERPROOF EXISTING FOUNDATION, DESIGN/BUILD FULL FACILITY RESTORATION GORDON M. CRAIG U.S. ARMY RESERVE CENTER, BROCKTON, MA |
Amount:
$5,099
Award Description: OVERTIME WORK (WEEKENDS) TO INSTALL VARIABLE FREQUENCY DRIVE (VFD) |
Amount:
$1,440
Award Description: TO PERFORM ADDITIONAL WORK TO REMOVE EXISTING 12X12 PANELS AND REPLACE WITH 24X24 |
Amount:
$1,965
Award Description: INSTALL TWELVE ADDITION DIMMABLE BALLASTS |
Amount:
-$40,571
Award Description: ARRA TO DEFINITIZE CONTRACT LINE ITEM 0001A. |
Amount:
$5,498
Award Description: TO INSTALL 12 ADDITIONAL DRAIN/SHUT OFF VALVES IN THE MEZZANINE CEILING AREA AT THE PROVIDENCE FEDERAL COURTHOUSE. |
Amount:
$106,338
Award Description: ARRA TO INSTALL REDESIGNED CHILL WATER PUMP AND BUFFER TANK AT THE PASTORE FEDERAL BUILDING.
UNDEFINITIZED CONTRACT ACTION |
Amount:
$8,100
Award Description: INSTALL SIXTY (60) CIRCUIT SETTERS IN OLDER FAN COIL UNITS. |
Amount:
$4,000
Award Description: TAS::21 2081::TAS ARRA::YES::ARRA CASE JC137 REVISE FINAL QUANTITY OF ASPHALT TO 171.95 TONS FOR ASPHALT LEVELING, FULL FACILITY RESTORATION OF GORDON M CRAIG U.S. ARMY RESERVE CENTER, BROCKTON, MA |
Amount:
$15,721
Award Description: TAS::21 2081::TAS ARRA::YES::ARRA CASE JC028 PROVIDE PULL STATION FOR ROOM 116; CASE JC096 REPAIR CRACK IN EXISTING RAIN LEADER; CASE JC099 INCREASE SIZE AND POWER REQUIREMENTS FOR KITCHEN EXHAUST FAN; CASE JC117 DELETE ASPHALT COLD PLANING IN THE MEP PARKING AREAS AND PAVEMENT; CASE JC126 REPLACE SODIUM LAMP FOR EXTERIOR LIGHT AND INSTALL CONDUIT, WIRE AND POWER SUPPLY PANELS FOR ELECTRIC MORTISE LOCKS; CASE JC131 CHANGE CHILLED WATER CONTROL VALVES FROM 2-WAY TO 3-WAY; CASE JC132 REPLACE FIRE HYDRANT, INSTALL ADDITIONAL KNOX BOX, AND ADD SINGLE MAN-GATE IN FENCE TO ALLOW ACCESS FOR FIRE DEPARTMENT, FULL FACILITY RESTORATION, GORDON M. CRAIG U.S. ARMY RESERVE CENTER, BROCKTON, MA |
Amount:
-$137
Award Description: TAS::21 2081::TAS ARRA::YES::ARRA CASES JC032, JC047, JC061, JC063R, JC70R, JC072, JC073, JC074, JC075 JC076, JC077, JC079 THROUGH JC093, JC095, JC097, JC101, JC102, JC104 THROUGH JC114, JC119, JC122, JC124, JC125, JC127 AND JC129 FOR MISCELLANEOUS CHANGES TO KITCHEN MECHANICAL AND ELECTRICAL SYSTEMS, REVISIONS TO LIGHTING IN SPECIFIED AREAS AND OTHER MISCELLANEOUS USER-REQUESTED CHANGES, FULL FACILITY RESTORATION, GORDON M. CRAIG U.S. ARMY RESERVE CENTER, BROCKTON, MA |
Amount:
$9,431
Award Description: TAS::21 2081::TAS ARRA::YES::ARRA CASE JC136 CONTRACT WITH VERIZON TO INSTALL OUTSIDE PLANT CABLING, FULL FACILITY RESTORATION OF THE GORDON M. CRAIG U.S. ARMY RESERVE CENTER, BROCKTON, MA |
Amount:
$0
Award Description: TO EXTEND THE CONTRACT COMPLETION DATE FROM 10/18/2011 TO 11/01/2011 TO ALLOW ENOUGH TIME TO COMPLETE BYPASS VALVE INSTALLATION. |
Amount:
$0
Award Description: TO EXTEND THE TASK ORDER COMPLETION DATE FROM 01/20/2012 TO 05/14/2012 TO ALLOW ENOUGH TIME TO COMPLETE THE COMMISSIONING (START UP, TESTING AND BALANCING) OF THE CONDENSING WATER SYSTEM WHICH NEEDS TO BE DONE IN THE SPRING. |
| Location Information |
| Latitude, Longitude |
0º 0' 0",
0º 0' 0" |
| Congressional District |
02 |
| City |
PROVIDENCE |
| County |
PROVIDENCE |
| State |
RI |
| Zip |
02903 |
|