contract- RECIPIENT AWARD SUMMARY

OUDENS AND KNOOP ARCHITECTS PC

Clarification of Codes


AWARD OVERVIEW

AWARD OVERVIEW
Agency Name: General Services Administration Project Location: PHILADELPHIA
Award Number: GSP0309AZ5078 Project Location - State: PA
Funding Amount: -$30,000 Project Location - Zip Code: 191061611
Ending Date: 2012-01-02 Congressional District: 01

RECIPIENT INFORMATION (AWARD)

RECIPIENT INFORMATION (AWARD)
Recipient Name: OUDENS AND KNOOP ARCHITECTS PC
Recipient Address: 2 WISCONSIN CIR STE 820
Recipient City: CHEVY CHASE
Recipient State: MD
Recipient Zip Code: 208157033
Congressional District: MD-08

DESCRIPTION OF WORK/SERVICE PERFORMED

RECOVERY: ARRA BYRNE GREEN CA SERVICES.






TRANSACTIONS

TRANSACTIONS

Other Awards

Other Awards
Amount: $10,917
Award Description: TAS::47 4543::TAS RECOVERY PROJECT TO PROVIDE LIGHTING UPGRADE SERVICE TO THE BOGGS LOBBY AND PLAZA RENOVATION PROJECT. LOCATION: WILMINGTON, DE
Amount: $1,289
Award Description: TAS::47 4543::TAS - PRE-DESIGN SUPPORT SERVICES AT THE BYRNE/GREEN COMPLEX IN PHILADELPHIA, PA
Amount: $9,208
Award Description: TAS::47 4543::TAS - PRE-DESIGN SUPPORT SERVICES AT THE BYRNE GREEN COMPLEX IN PHILADELPHIA, PA.
Amount: $130,878
Award Description: TAS::47 4543::TAS - ARRA DESIGN SUPPORT SERVICES AT THE BYRNE GREEN COMPLEX IN PHILADELPHIA, PA
Amount: $47,520
Award Description: BOUNDARY SERVICES FOR THE SOCIAL SECURITY ADMINSTRATION NATIONAL SUPPORT CENTER
Amount: $2,205
Award Description: RECOVERY - SSA NATIONAL SUPPORT CENTER THIS MODIFICATION PROVIDES FOR CHANGES TO THE BOUNDARY STUDY SCOPE OF WORK
Amount: $50,082
Award Description: GEOTECHNICAL SERVICES FOR THE SOCIAL SECURITY ADMINISTRATION NATIONAL SUPPORT CENTER
Amount: $70,544
Award Description: TAS::47 4543::TAS RECOVERY PROJECT TO PROVIDE LIGHTING UPGRADE SERVICE AND CONSTRUCTION ADMINISTRATION SERVICES TO THE BOGGS LOBBY AND PLAZA RENOVATION PROJECT IN WILMINGTON, DE OUDENS + KNOOP TO PROVIDE POST-DESIGN A/E CONSTRUCTION ADMINISTRATION SERVICES.(CA)
Amount: $1,985
Award Description: TAS::47 4543::TAS PROJECT: "AMERICAN REINVESTMENT RECOVERY ACT " BOGG'S LOBBY AND PLAZA RENOVATION - PS07 LOCATION: J. CALEB BOGGS COURTHOUSE, WILMINGTON, DE PJ8C01223 THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO BY GENERAL SERVICE ADMINISTRATION AND OUDENS+KNOOP IAW FAR 43.103(A). PER PROPOSAL DATED 05/25/10 FOR REVISING, UPDATING AND REISSUING DRAWINGS FOR THE TEMPORARY SCREEENING FACILITY; THE GOVERNMENT AGREES TO INCORPORATE THE CONTRACTOR'S (OUDENS + KNOOP) PROPOSAL INTO THE CONTRACT BY WHICH BOTH PARTIES MUTUALLY AGREE TO THE STATED PROPOSAL. THE MODIFICATION HEREBY PROVIDES THE DESIGN MODIFICATION FOR THE TEMPORARY SCREENING FACILITY.
Amount: $2,498
Award Description: TAS::47 4543::TAS +RECOVERY+ LOBBY EXPANSION/ENERGY LIGHTING UPGRADES PROJECT " GSA IS REQUESTING OUDENS + KNOOP ATTEND EPM TRAINING AS PART OF THE +RECOVERY+ LOBBY EXPANSION/ENERGY LIGHTING UPGRADES PROJECT TAKING PLACE AT J. CALEB BOGGS U.S. COURTHOUSE AND FEDERAL BUILDING IN WILMINGTON, DE
Amount: $110,426
Award Description: TAS::47 4543 ::TAS RECOVERY ARRA BYRNE GREEN PRE-DESIGN SUPPORT SERVICES TASK ORDER: MODIFICATION TO INCLUDE CA SERVICES
Amount: $0
Award Description: TAS::47 4543::TAS - RECOVERY PRE-DESIGN SUPPOERT SERVICES
Amount: $0
Award Description: RECOVERY - PRE-DESIGN SUPPORT SERVICES TASK ORDER EXTENSION
Amount: $71,328
Award Description: ARRA: A/E SERVICES FOR THE GIVEN SCOPE OF WORK, WHICH INCLUDE AHU AND HVAC UPGRADE STUDY IN THE BYRNE COURTHOUSE IN PHILADELPHIA, PA.
Amount: $3,518
Award Description: TAS::47 4543::TAS PROJECT: "AMERICAN REINVESTMENT RECOVERY ACT " BOGG'S LOBBY AND PLAZA RENOVATION LOCATION: WILMINGTON, DE - THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE EPM TRAINING TO THE DESIGNATED A/E WORKING ON THE PROJECT.
Amount: $9,906
Award Description: PROJECT: +ARRA+ BOGG'S LOBBY AND PLAZA RENOVATION +PS10 LOCATION: J. CALEB BOGGS COURTHOUSE, WILMINGTON, DE . THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO BY GENERAL SERVICE ADMINISTRATION AND OUDENS+KNOOP IAW FAR 43.103(A). PER PROPOSAL DATED 08/23/10 FOR ASBESTOS AIR MONITORING AND RELATED SERVICES; THE GOVERNMENT AGREES TO INCORPORATE THE CONTRACTOR'S (OUDENS + KNOOP) PROPOSAL INTO THE CONTRACT BY WHICH BOTH PARTIES MUTUALLY AGREE TO THE STATED PROPOSAL. THE MODIFICATION HEREBY REQUESTS THE A/E TO PROVIDE MANAGEMENT SERVICES DURING THE ASBESTOS ABATEMENT PROJECT.
Amount: $1,761
Award Description: TAS: 47 4543: :TAS PROJECT" AMERICAN REINVESTMENT RECOVERY ACT" BOGG'S LOBBY AND PLAZA RENOVATION - PS09. LOCATION: J. CALEB BOGGS COURHOUSE, WILMINGTON, DE PJ8C01223. MDIFICATION PS09 HEREBY DIRECTS THE O+K TO COMPLETE A SURVEY TO DETERIMINE THE PRESENCE OF ASBESTOS-CONTAINING MATERIALS ASSOCIATED WITH BOGGS COURHOUSE BUILDING. THE AREA CONTAINING HAZARDOUS MATERIAL HAS BEEN IDENTIFIED IN THE PICTURE WHICH HAS BEEN PROVIDED TO O+K. O+K AND THEIR SUBCONSULTANTS WILL CONDUCT TESTIN ON THE MATERIALS FOR EVIDENCE OF ACBM AND MAKE RECOMMENDATIONS TO GSA, SO THAT THE GOVERMENT CAN TAKE CORRECTIVE ACTION.
Amount: $45,384
Award Description: PROJECT TITLE: DESIGN POST OFFICE FLOORING REPLACEMENT, POCH, 7TH & GRANT STREETS, PITTSBURGH, PA THE PURPOSE OF THIS MODIFICATION IS AS FOLLOWS: YOUR PROPOSAL DATED JULY 22. 2010 FOR ADDITIONAL CONSTRUCTION ADMINISTRATION SERVICES ASSOCIATED THE POCH FLOOR REPLACEMENT WHICH ARE NECESSARY TO ACCOMPLISH THIS PROJECT, ARE ACCEPTED AND HEREBY INCORPORATED INTO DELIVERY ORDER GS-03P-03-08-CD-5097 UNDER CONTRACT GS-03P-05-DX-D-0024. THE TOTAL AMOUNT OF THIS DELIVERY ORDER IS INCREASED BY $45,384.00 FROM $81,830.00 TO $127,214.00. THE ANTICIPATED DATE FOR COMPLETION OF THESE SERVICES IS AUGUST 19, 2011. ALL OTHER TERMS AND CONDITIONS REMAIN THE SAME.
Amount: $0
Award Description: CLOSE OUT
Amount: -$3,678
Award Description: GEOTECHNICAL SERVICES FOR THE SSA NATIONAL SUPPORT CENTER. THIS MODIFICATION DELETES PREVIOUSLY AWARDED WORK AND ADDS AN ADDITIONAL GEOTECH SURVEY.
Amount: $3,967
Award Description: THIS MODIFICATION IS TO PROVIDE FOR ADDITIONAL BOUNDARY SERVICES FOR THE SSA NATIONAL SUPPORT CENTER PROJECT
Amount: $2,824
Award Description: BOUNDARY SURVEY FOR SSA NATIONAL SUPPORT CENTER - THIS MODIFICATION EXERCISES AN OPTION TO PROVIDE AN UPDATED BOUNDARY SURVEY
Amount: -$3,992
Award Description: BOUNDARY SURVEY FOR SSA NATIONAL SUPPORT CENTER. THIS MODIFICATION DELETES BOUNDARY THAT IS NO LONGER NEEDED AS WELL AS ADDS ADDITIONAL BOUNDARY WORK IN SUPPORT OF THE SITE SELECTION PROCESS FOR THE SSA NATIONAL SUPPORT CENTER PROJECT.
Amount: $12,555
Award Description: TAS::4543::TAS PROJECT: +ARRA+ REGION WIDE FULL SERVICE A/E/BOGG'S LOBBY AND PLAZA RENOVAT/PS13- NEGATIVE PRESSURE THE MODIFICATION HEREBY REQUESTS THE A/E TO PROVIDE AN INVESTIGATIVE REPORT TO IDENTIFY AND PROVIDE SOLUTIONS TO THE NEGATIVE PRESSURE BEING EXPERIENCED AT THE SUBJECT PROPERTY.
Amount: $34,579
Award Description: TAS::47 4543::TAS PROJECT: "AMERICAN REINVESTMENT RECOVERY ACT " BOGG'S LOBBY AND PLAZA RENOVATION J. CALEB BOGGS FEDERAL BUILDING. 844 KING STREET, WILMINGTON, DE CONTRACT NO. GS-03P-05-DX-D-0024/GS-P-03-08-AZ-5062/PS11 - THIS MODIFICATION WILL PROVIDE FOR AN EQUITABLE ADJUSTMENT TO THE FIRM (O+K) FOR CONTINUES CONSTRUCTION ADMINISTRATION SERVICES FOR A PERIOD OF TWO MONTHS TO COMPETE THE PROJECT.
Amount: $9,198
Award Description: THE PURPOSE OF MODIFICATION PS14 IS TO HAVE THE A/E PERFORM AIR-MONITORING SERVICES AS PART OF THE "ARRA" BOGGS LOBBY&PLAZA RENOVATION PROJECT.
Amount: $3,675
Award Description: TAS::47 4543::TAS PROJECT "AMERICAN REINVESTMENT RECOVERY ACT" BOGG'S LOBBY AND PLAZA RENOVATION. J CALEB BOGGS FEDERAL BUILDING, 844 KING STREET, WILMINGTON DE. CONTRACT NO. GS03P05DXD0024 - THE GOVERNMENT AGREES TO INCORPORATE THE CONTRACTOR'S (OUDENS + KNOOP) PROPOSAL INTO THE CONTRACT BY WHICH BOTH PARTIES MUTUALLY AGREE TO THE STATED PROPOSAL. THE MODIFICATION HEREBY PROVIDES FOR AN EQUITABLE ADJUSTMENT TO THE A/E FOR STRUCTURAL ENGINEERING SERVICES RENDERED AS PART OF THE SUBJECT PROJECT. THIS MODIFICATION THEREBY INCREASES THE TOTAL CONTRACT AMOUNT BY $3,675.00 $ FROM $ 252,132.80 TO $ 255,807.80
Amount: -$30,000
Award Description: RECOVERY: ARRA BYRNE GREEN CA SERVICES.
Amount: $0
Award Description: CLOSEOUT MODIFICATION
Amount: -$8,962
Award Description: PROJECT TITLE: DESIGN POST OFFICE FLOORING REPLACEMENT, POCH, 7TH&GRANT STREETS, PITTSBURGH, PA CLOSE OUT / DEOBLIGATION MOD
Amount: -$3,747
Award Description: THE PURPOSE OF THIS MODIFICATION IS TO DEDUCT $3,747.54 FROM PS14, FOR SERVICES RENDERED AFTER THE PERIOD OF PERFORMANCE WAS SHORTENED FROM 10 DAYS TO 5 DAYS.

Project Location Detail

Location Information
Latitude, Longitude 0º 0' 0", 0º 0' 0"
Congressional District 01
City PHILADELPHIA
County PHILADELPHIA
State PA
Zip 19106