| Other Awards |
Amount:
$8,668,174
Award Description: TAS::47 4543::TAS MECHANICAL, ELECTRICAL AND PLUMBING REPLACEMENT PROJECT AT THE BISHOP HENRY WHIPPLE FEDERAL BUILDING IN FT. SNELLING, MN. ARRA::YES::ARRA |
Amount:
$753,454
Award Description: TAS::36 0158::TAS AE DESIGN SERVICES TO REPLACE THE WATER DISTRIBUTION SYSTEM AT THE EDWARD HINES JR. VA HOSPITAL, HINES IL |
Amount:
$232,489
Award Description: TAS::47 4543::TAS
MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PC14 DESIGN AND CONSTRUCTION ADMINISTRATIVE (CA) SERVICES FOR OCCUPIED BUILDING SCENARIO.
|
Amount:
$13,662
Award Description: TAS::47 4543::TAS
MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PS02 + SITE SURVEY. |
Amount:
$420,586
Award Description: TAS::47 4543::TAS
MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PS05 + CONSTRUCTION ADMINISTRATION SERVICES FOR ADDITIONAL WORK. |
Amount:
$299,563
Award Description: MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PS08, ADDITIONAL DESIGN AND CONSTRUCTION ADMINISTRATION FOR SWING SPACE. |
Amount:
$213,218
Award Description: TAS::47 4543::TAS
MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PC12, DESIGN AND CONSTRUCTION ADMINISTRATIVE (CA) SERVICES FOR SITE DESIGN
|
Amount:
$2,842
Award Description: TAS::47 4543::TAS
MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PS01 + MOTORPOOL HAZARDOUS MATERIAL SURVEY. |
Amount:
$19,204
Award Description: TAS::47 4543::TAS
MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PS10, ADDITIONAL DESIGN SERVICES RELATED TO BIM. |
Amount:
$1,845,000
Award Description: TAS::47 4543::TAS
MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PS04 + DESIGN SERVICES FOR ADDITIONAL SCOPE. |
Amount:
$0
Award Description: TAS::47 4543::TAS
MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PA13 -CORRECTION TO PS05. |
Amount:
$4,812
Award Description: TAS::47 4543::TAS
MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PS03; OVERALL STUDY FOR PRE-DESIGN AND CONCEPT LEVEL. |
Amount:
$29,285
Award Description: TAS::47 4543::TAS
MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PS09, ADDITIONAL DESIGN SERVICES FOR PREDESIGN STUDY OF POTENTIAL ENHANCEMENTS. |
Amount:
$5,818
Award Description: TAS::47 4543::TAS
MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PS07, GEOTECHNICAL TESTING AND REPORTING. |
Amount:
$100,904
Award Description: TAS::47 4543::TAS
MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PC15 DESIGN AND CONSTRUCTION ADMINISTRATIVE (CA) SERVICES FOR KITCHEN MODERNIZATION. |
Amount:
$20,930
Award Description: TAS::47 4543::TAS
MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PS11, TOPOGRAPHICAL/UTILITY AND BOUNDARY SURVEY SERVICES. |
Amount:
$478,862
Award Description: TAS::47 4543::TAS
MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PS06 +DESIGN AND CONSTRUCTION ADMINISTRATION FOR THE SALLYPORT AND MOTORPOOL. |
Amount:
$0
Award Description: MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PA16- CORRECTION OF DELIVERY DATE.
|
Amount:
$216,157
Award Description: MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PS17 - DESIGN INTENT DOCUMENTS FOR VETERAN'S ADMINISTRATION. |
Amount:
$55,747
Award Description: S/A #1 FOR ADDITIONAL AE SERVICES AT THE EDWARD HINES JR. VA HOSPITAL, HINES IL |
Amount:
$39,946
Award Description: MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PS33 -CONSTRUCTION ADMINISTRATION SERVICES FOR TRANSFORMER. |
Amount:
$114,529
Award Description: MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PS24 - ENTRY CANOPY. |
Amount:
$18,710
Award Description: MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PS22 - UPDATE BUILDING DESIGN STANDARD. |
Amount:
$880,000
Award Description: MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PC23 - ADDITIONAL CONSTRUCTION ADMINISTRATION SERVICES. |
Amount:
-$98,592
Award Description: MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PS30 - FEE CREDIT. |
Amount:
$97,492
Award Description: MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PS20 - WINDOWS. |
Amount:
$520,000
Award Description: MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PS26 - ADDITIONAL DESIGN SERVICES. |
Amount:
-$18,710
Award Description: MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PA31 - CHANGE FUNDING SOURCE FOR BUILDING DESIGN STANDARD. |
Amount:
$96,730
Award Description: MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PS25 - SWITCHGEAR. |
Amount:
$24,228
Award Description: MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PS21 - MEPS TI FIT. |
Amount:
$37,402
Award Description: MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PC19 - GROUND HEAT EXCHANGER |
Amount:
$174,925
Award Description: MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PC18 - TESTING SERVICES FOR GEOTHERMAL WELL FIELDS. |
Amount:
$285,799
Award Description: OTHER FUNCITON - S/A #2 FOR ADDITIONAL AE SERVICES AT THE EDWARD HINES JR. VA HOSPITAL, HINES IL |
Amount:
$0
Award Description: MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PA44 CORRECTION TO PS43. |
Amount:
-$340
Award Description: MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PS50 PDL TO FIRM OF PC19. |
Amount:
-$187,302
Award Description: MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PS40 DEOBLIGATION OF FUNDS. |
Amount:
-$216,157
Award Description: MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PS43 DEOBLIGATION OF PS17. |
Amount:
$0
Award Description: MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PS48 PDL TO FIRM OF PC15 |
Amount:
$0
Award Description: MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PS49 PDL TO FIRM OF PC18. |
Amount:
$0
Award Description: MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PA42. |
Amount:
$187,302
Award Description: MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PS41 - VARIOUS CES. |
Amount:
$0
Award Description: MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PS47 PDL TO FIRM OF PC14. |
Amount:
$0
Award Description: MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PS46 PDL TO FIRM OF PC12. |
Amount:
-$1,390,991
Award Description: MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; MODIFICATION PC51 -DEOBLIGATION. |
Amount:
$5,950
Award Description: MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; CE2070, MODIFICATION PS59 - CHANGES TO TENANT VBA SPACE. |
Amount:
$1,067
Award Description: AE SERVICES
MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; CE2056, MODIFICATION PS53 - TESTING AND OBSERVATION. |
Amount:
$61,563
Award Description: MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; CE2076, MODIFICATION PS56 - HAZARDOUS MATERIAL TESTING SERVICES. |
Amount:
$6,740
Award Description: AE SERVICES - DESIGN
MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; CE2060, MODIFICATION PS54 - ELEVATOR REDESIGN. |
Amount:
$3,560
Award Description: DESIGN SERVICES- AE MECHANICAL, ELECTRICAL AND PLUMBING (MEP) REPLACEMENT FOR THE BISHOP HENRY WHIPPLE FEDERAL BUILDING LOCATED IN FT. SNELLING, MINNESOTA; CONTRACT NUMBER GS-05P-09-GB-D-0022, DELIVERY ORDER GS-P-05-09-GB-5033; CE2061, MODIFICATION PS55 - EXTERIOR SHELTER AND GABION WALL. |